
Library >> Global
Energy Trends >> Existing
Transmission Grids
Mexico, Vietnam, and Central
America Transmission Grids
"Mexico has a national interconnected power grid divided
into four regional divisions: Northern, North Baja,
South Baja, and Southern (the largest). Northern Mexico
is connected to the U.S. grid, and additional interconnections
are planned.
In July 2000, a cable from Eagle Pass, Texas to Piedras,
Mexico connected U.S. utility AEP and CFE's transmission
systems. This is a new kind of electric connection,
using asynchronous HVDC (high-voltage direct-current)
technology to combat the problem of differing power
currents between countries.
A New Mexico utility is working on a project to connect
a power station outside of Phoenix, Arizona to CFE's
system in Sonora, Mexico. A proposed project aims
to link Tucson, Arizona to points south of the U.S.-Mexican
border. Along the Mexican-California border in Baja
California, new plants are under construction to meet
growing demand in Baja and to allow Mexico to increase
electricity exports to U.S. markets."
http://www.eia.doe.gov/cabs/mexico.html
-----
"The state power company, Electricity of Vietnam
(EVN), is working on a plan to develop a national
electricity grid by 2020. By 2005, EVN aims to build
hydropower plants in the central and central highland
regions. Three hydroelectric dams, with capacities
of between 285 MW and 370 MW, are planned, with the
construction of the first at Dai Ninh set to begin
in 2001."
"A North-South power cable transmits electricity
from Vietnam's largest generator, the Hoa Binh hydropower
plant in the north, to large population centers in
the south, linking the country into one electricity
grid. The cable has helped to alleviate an electricity
shortage in Ho Chi Minh City.
The government currently is considering building
more cables. Plans are underway to build an underground
electric cable, an above-ground cable, and a transformer
station in Tao Dan (in the Ho Chi Minh City area).
Construction began in mid-2000 and is to finish in
2002. The $56-million project is being funded by the
World Bank. The World Bank also is funding a $201-million
project to extend distribution infrastructure into
rural areas currently without electricity."
http://www.eia.doe.gov/cabs/vietnam.html
-----
"Currently there are few electricity interconnections
among the Central American nations. Guatemala's and
El Salvador's power grids are linked via a 230-kV
interconnect, and a separate link connects Honduras,
Nicaragua, Costa Rica and Panama, but many of the
interconnects are old and unreliable.
Six Central American nations (not including Belize)
have discussed the construction of a Central American
power grid, Sistema de Interconexion Electrica para
America Central (SIEPAC). The countries have discussed
the possibility of interconnecting their transmission
grids in order to alleviate periodic power shortages,
reduce operating costs, optimize regional use of hydroelectric
power, create a competitive market in the region,
and attract foreign investment.
The countries also are considering the creation of
a regional electric power market. The SIEPAC project
could cost more than $300 million, with the Inter-American
Development Bank (IDB) having pledged $170 million,
the Spanish government $70 million, and the Central
American nations $106 million.
SIEPAC calls for 1,125 miles of transmission lines,
with a capacity of 300 MW between Guatemala and Panama,
as well as improvements to existing systems. SIEPAC
likely will involve upgrading links and building 230-kV
links between Guatemala and Honduras, and Honduras
and El Salvador.
In the future, the private sector could own a stake
and, eventually, state-owned power generators in some
countries could be in direct competition with private
plants in other countries. In addition, there are
plans for a second interconnection, along the same
route."
http://www.eia.doe.gov/emeu/cabs/centam.html
-----
From the US Energy Information Administration
(EIA) Country Analysis Briefs
http://www.eia.doe.gov/cabs/

|