Tres Amigas Technology Holds
Promise for Expanding Renewable Energy Supply
Jun. 2, 2011 - Teresa Hansen - elp.com
A few months ago, New Mexico Governor and former
U.S. Energy Secretary Bill Richardson announced
that his state will be home to an energy transmission
project that will connect the three main U.S. power
grids.
The Tres Amigas SuperStation will allow energy
to be shared among the Eastern Interconnection,
Western Interconnection—known as the Western
Electricity Coordinating Council (WECC)—and
Texas Interconnection—known as the Electric
Reliability Council of Texas (ERCOT). Tres Amigas
LLC CEO Phil Harris developed the SuperStation
concept and conducted its initial research and
design. He is the former CEO of PJM Interconnection,
the world’s largest transmission balancing
area with more than 240,000 MW under management.
“After I retired from PJM, I worked in China
and Europe on high-voltage transmission projects,” Harris
said. “I knew there was a lot of interest
and need for a high-voltage interconnection in
the United States, and I’m originally from
New Mexico.”
The project’s main goal is to create a first-of-its-kind
market hub through which potential U.S. renewable
energy can be developed and delivered to load centers.
The project will be the proving ground for superconductor
electricity pipeline technology. It also promises
to increase the U.S. power grid’s reliability
and security. Its strategic partners are American
Superconductor, AltEnergy LLC and ZGlobal Inc.
Several studies from the Western Governors’ Association,
EPRI working groups and Department of Energy focused
on the need for an interconnection have identified
Texas and New Mexico as ideal locations because
the three interconnections are closest to one another
there.
New Mexico wanted the project and agreed to a
99-year land lease, said Jack McCall, American
Superconductor director of business development
HTS T&D systems.
“New Mexico had the space and allowed us
to lease 22 square miles of land, or about 14,400
acres, near Clovis,” McCall said.
The eastern New Mexico city is near the borders
of Colorado, Oklahoma and Texas—states with
a lot of wind and solar energy potential. Many
wind and solar developers are interested in the
project, Harris said.
“The nation needs large renewables, and
people want green power,” Harris said. “This
facility will allow much of the nation’s
wind energy to be harnessed and transported to
areas where it’s needed. If this was an oil
field find, it would be as big as Purdue Bay.”
Clovis is also close to several major transmission
projects. So far, five transmission companies—Public
Service Co. of New Mexico, ITC, Excel Energy, American
Electric Power and Sharyland Utilities—via
letters of intent have committed to connecting
to Tres Amigas, and more are in negotiations.
The Transmission Bottleneck
To understand how and why Tres Amigas is a groundbreaking project, one must
know how electricity flows—or doesn’t flow—among North
American power grids now. Each of the three grids can transfer electricity
to another through a direct current (DC) converter link. Typically, alternating
current (AC) power from transmission lines is converted in one grid to direct
current (DC) as an intermediate power form at a substation. The power is
then re-converted from DC back to AC before reaching the adjacent grid. This
synchronizes power flows. This transfer can occur only between two grids.
In other words, electricity can be transferred from one grid to another grid,
but not among all three at the same time. Never have all three grids been
united at one time.
Currently 10 DC converter links exist in North
America. Seven links connect the Eastern Interconnection
and WECC grids in the U.S., and one connects the
two in Canada. In addition, two links connect ERCOT
to the Eastern Interconnection. No interconnection
exists between ERCOT and the WECC. Most of the
DC converter links carry 100-200 MW of electricity
each. One of the two that connects ERCOT to the
eastern grid is 600 MW, which is the largest exchange.
The total capacity of all 10 is about 2.3 GW.
Tres Amigas initially will be able to carry up
to 5 GW of electricity at a time but will be scalable
and can expand to 30 GW, Harris said.
“Tres Amigas will be an open-access facility
and will likely continue to grow for many years,” he
said. “Construction will continue like in
the space station. We will add voltage-sourced
converters as more companies tie into the facility.”
Tres Amigas Technology
The Tres Amigas SuperStation will employ the latest power grid technologies,
including three high-voltage DC (HVDC) terminals created from voltage source
converters (VSCs). The HVDCs, each of which has a 5-GW capacity, will be
placed about 2 miles apart in a triangle-shaped loop (see Figure 2). The
terminals will be connected by an underground DC superconductor cable (pipeline)
that can carry more than 5 GW of electricity with no electrical loss. Each
HVDC terminal also will be equipped with an advanced battery system.
| 2 Tres Amigas SuperStation |
 |
The VSCs used for the terminals are power electronics
systems that allow multi-terminal access to and
from DC lines and cables, McCall said.
“There won’t be a single 5-gigawatt
line coming into each terminal, but three to five
lines coming into each one,” McCall said. “You
don’t want all the transmission lines coming
into one terminal; you want them to be spread apart.”
Voltage converters are much more robust than old-technology
DC links, Harris said. VSC technology is being
used in more than a dozen locations around the
world.
Installed at the interconnection point of each
of the three U.S. power grids, the VSC terminals
will transition the AC power flowing from the powerlines
feeding into the SuperStation into DC power and
then will transition DC power into AC power at
the adjacent grids.
Harris said the project will be similar to a highway
rotary used for traffic flow with the superconductor
cables serving as the main pathway for electricity,
and VSCs serving as on-ramps and off-ramps for
the power.
The DC superconductor cable technology that will
provide the pathway for the electricity was developed
within the past decade. The concept of using superconductor
cable for DC power transmission originated with
an EPRI report completed in 1997. The more general
concept of using superconductor cable for long-distance,
high-power transmission, however, dates back to
at least 1967.
The cable can carry gigawatts of power with 100
percent efficiency among the SuperStation’s
three converter stations. The cable will be contained
in a 3-foot underground pipeline similar to those
used in the oil and natural gas industries. Superconductor
cables are more power-dense and efficient than
other transmission options. Their underground nature
also significantly enhances system security and
reliability, McCall said.
“Overhead transmission lines could be used,” he
said, “but it would take three to four overhead
circuits to move what the underground pipeline
can move. Also, overhead is less reliable and secure
than underground, and traditional underground transmission
would need eight to 10 DC lines, which would require
a large right-of-way and would result in large
power losses.”
Because superconductor cable carries higher voltage,
it has less voltage losses: zero, McCall said.
“Superconductor pipeline was originally
looked at for long-distance transmission due to
its lack of line losses, easier siting requirements
and right-of-way needs, as well as lower cost allocation
based on the amount of electricity that can be
moved,” McCall said. “It was also envisioned
to have many terminals so that electricity input
and off take could occur along the line.”
Tres Amigas, which will use only a 6-mile loop
and three terminals, is a different application
than what was originally envisioned. Because it
will be transporting such high-level DC power,
however, the technology makes sense, McCall said.
“Tres Amigas is exciting because it will
develop and prove superconductor pipeline technology
outside a lab,” McCall said.
The technology has been proven in the lab and
in numerous demonstration projects, but it is a “big
leap of faith” for a transmission company
or utility to invest in 1,000 miles of the technology
without any history of it working in long-distance,
high-voltage settings, McCall said.
“Tres Amigas is the perfect project for
the technology because it needs high-voltage transmission,
but doesn’t need many miles of it,” he
said.
VSCs on a typical DC circuit mostly are limited,
and higher voltages aren’t possible. The
voltage can be increased, but the current also
must be increased, resulting in higher losses.
VSCs usually are used for lower-current or short
distances.
“Superconductor cables have allowed voltage
source converters to come into their own,” McCall
said. “Superconductor cable can transmit
high voltages without increasing current, thus
eliminating losses.”
Because most of the megawatts entering the SuperStation
will be generated with intermittent renewable energy
sources, it must be able to handle numerous charge-discharge
cycles. Tres Amigas, therefore, will be equipped
with batteries to provide short-term energy storage,
mainly to keep the system balanced, McCall said.
“Tres Amigas will serve as its own balancing
authority,” McCall said. “The electricity
coming in must equal the electricity going out.”
The battery storage also will allow Tres Amigas
to store some electricity and resell it—an
ancillary product of energy storage. It also will
provide reactive system support, enhancing grid
reliability and power quality.
Tres Amigas developers have not selected the battery
technology and supplier, but they are considering
proven technologies and designs that will complement
energy transfer while providing optional ancillary
services.
Right Technology, Right Market
Tres Amigas developers are convinced that the
technology and business environment are right for
this project, Harris said.
“There is a national interest in this project,
and it addresses a national need,” Harris
said. “It is in the nation’s best interest
to build this facility.”
The project will create one market out of three,
said David Raskin, a partner at the Washington
office of Steptoe & Johnson LLP and counsel
for Tres Amigas.
“It’s a market expander, and as such
will create additional opportunities and investment
incentives for renewable power,” Raskin said.
It will incent development beyond just the renewable
portfolio standards that are driving much of the
current renewable energy development, he said.
Tres Amigas appeals to generators and suppliers
for a couple of reasons. First, if the marginal
price at one side of the facility (in one of the
three grids) is different than at the other side,
suppliers or generators will be interested in selling
into the other grid. Second, demand for renewables
is increasing nationwide. Texas has a lot of wind
power, but ERCOT is almost saturated with wind.
The state can only develop its potential wind and
solar power if it can move some of that power onto
the other grids. New Mexico has a lot of potential
solar power and wants to expand its market. Tres
Amigas is in the perfect place to allow renewable
energy to be moved to load centers where it can
be used.
Tres Amigas also will serve as an anchor to the
nation’s transmission system, Raskin said,
improving its reliability. The electrical engineering
features of the VSCs will provide reactive power
to the system, providing support to large transmission
lines coming into the facility and making the grid
more stable.
“Without the VSC and pipeline superconductor
technology, the facility would not be possible,” Raskin
said. “This is an example of the right technology
coming along at just the right time. The facility
would not have been possible even three to five
years ago.”
The Business Model
Tres Amigas differs from any transmission project
ever built, but it is still a merchant transmission
project and falls under Federal Energy Regulatory
Commission (FERC) regulations, Raskin said.
“Transmission is a highly regulated business
and usually considered a monopoly,” Raskin
said.
In early December 2009, Raskin filed two FERC
applications that must be approved for the $1 billion
project to attract needed investors. One of those
filings will determine how Tres Amigas can establish
transmission rates and collect on those rates.
“Unlike most transmission system owners,
Tres Amigas will have no captive customers,” Raskin
said. “The developers are taking a major
market risk. In turn, they want pricing flexibility
to charge what the market will bear. They must
have the requested pricing approval to ensure they
can make money and thus obtain financing.”
FERC has two models for establishing and collecting
transmission rates, Raskin said.
One is a cost-based model that normally applies
to transmission providers with captive customers
that bear responsibility for transmission costs
under an individual or regional open-access transmission
tariff or other transmission arrangement. This
is the typical model for a regulated investor-owned
utility.
The other is based on merchant transmission rate
setting. In this model, a transmission company
takes the market risk and can charge negotiated
rates. Merchant transmission companies hold open
auctions and sell capacity based on what the market
will bear. The price depends on the difference
between energy costs at the two ends of the line.
For example, if electricity is selling for 10 cents
a kWhr at one end of the line and 20 cents a kWhr
at the other, then a company might be willing to
pay 10 cents to send its power across the lines.
“Tres Amigas is different than any merchant
transmission company,” Raskin said. “Transmission
companies are looking for customers to buy capacity
under long-term contracts—20 to 30 years.”
Tres Amigas needs more flexibility than a traditional
merchant transmission company because it must offer
short- and medium-term pricing. Because it’s
a market hub, transactions must be offered based
on market conditions at a particular time. These
conditions can and will change, Raskin said.
“If limited to long-term pricing, we may
not have the flexibility necessary to make Tres
Amigas economically successful,” he said. “We
can’t rely on history to tell us what the
market will be. I think FERC will recognize this
as being a great opportunity to move renewable
energy forward and open up power markets.”
The second FERC application Raskin filed requests
that the commission allow ERCOT to remain separate
and independent from FERC regulations.
“Tres Amigas is a market expander for ERCOT,” Raskin
said. “But at the same time, Texas places
great value on its independence from FERC. Even
if the economic benefits are major, I would be
very shocked if Texas would give up ERCOT’s
independence. The separation of ERCOT from FERC
control is a foundational aspect of electricity
law in the United States. Tres Amigas should not
change that. In addition, I don’t believe
FERC has any interest in controlling ERCOT.”
By law, FERC must rule on the Tres Amigas application
within 60 days of the filing: Feb. 6, a Saturday,
so the ruling likely will come Feb. 5.
The ruling can be delayed if FERC comes back to
Raskin with questions or a request for more information.
Also in the next 60 days, opponents of the project
can provide FERC with concerns and opinions, which
could delay the ruling. That’s not too likely,
Raskin said.
“I currently don’t know of any constituency
that would have reason to oppose the project,” he
said. “Many are filing in support of it.
“The industry’s reaction to Tres Amigas
has been very favorable. It has truly been a unique
outpouring of support. I’m hopeful and confident
that FERC rules in our favor on both filings.”