Inga: 
                                Promise 
                               MAY 18, 2004 Business In Africa 
                                Online 
                               
                              
                              The development of Inga-3 is now associated with 
                              the Western Power Corridor (WESTCOR), a joint venture 
                              company registered in Botswana. WESTCOR aims to 
                              transmit power from Inga-3 in the DRC to South Africa 
                              via Angola, Namibia and Botswana. Once the WESTCOR 
                              Joint Venture Company is formed, equal equity contributions 
                              from the five national utilities and their chosen 
                              partners will make up the equity portion and security 
                              package for the debt portion of the project financing. 
                              International financiers will be encouraged to participate 
                              and to take up debt financing. Considerable support 
                              is also expected via the NEPAD initiative. There 
                              are three main components in the implementation 
                              of the WESTCOR project: 
                              
                                - The development of the Inga-3 power station 
                                  is estimated to cost US$3.74 billion 
                                
- Two 1,500MW converter stations will be constructed 
                                  at a basic cost of approximately US$421 million 
                                  each, totalling US$842 million. Upgrades for 
                                  the two existing stations along the lines will 
                                  be included in the HVDC installation cost. 
                                
- Converter stations - HVDC transmission lines: 
                                  The two South African termination points are 
                                  3,000 to 3,500 km from Inga-3. The total estimated 
                                  cost for the transmission lines, including the 
                                  terminations in South Africa, is US$652 million. 
                                
Inga site characteristics 
                              
Inga site is situated at a latitude of almost 
                                six degrees south and 14 degrees east in the DRC. 
                                It is about 150km upstream of the mouth of the 
                                Congo River and 225km downstream from Kinshasa. 
                                The Congo River, with an average flow rate of 
                                42,000 cubic metres per second, is the second 
                                largest river in the world after the Amazon. Among 
                                the big rivers of the world, it is the only one 
                                that has a significant slope in its lower course. 
                                For instance, in a distance of 15km, the natural 
                                difference in height is 102 metres. This series 
                                of rapids makes the Inga site the biggest source 
                                of hydro power in the world at a single point; 
                                the unbridled energy passing the point amounts 
                                to approximately 370 billion kWh per annum. Inga's 
                                yearly minimum flow rate is not less than half 
                                the annual maximum flow rate and this makes the 
                                river stable and suitable for power generation. 
                                The historical minimum flow rate was recorded 
                                in 1905 and was 21,400 cubic metres per second. 
                                The historical maximum flow rate, 84,400 cubic 
                                metres per second, was recorded in 1961. 
                              
Development of the Inga site 
                              
The overall development of the site foresaw four 
                                stages grouped into two phases. The first stage 
                                was the use of the Nkokolo valley to its maximum 
                                potential, while the second phase was the construction 
                                of the Grand Inga. The Nkokolo valley scheme does 
                                not require building a dam over the whole river. 
                                It uses a disused river bed that is closed off 
                                by the Shongo dam at the lower end. This gives 
                                a head of 60 metres to a part of the water diverted 
                                from the river at a point 8 km upstream. The scheme 
                                involves three stages of development: 
                              
                                - Inga-1 Power Station (commissioned in 1972) 
                                
- Inga-2 Power Station (commissioned in 1982) 
                                
- Inga-3 Power Station (planned). The development 
                                  of Inga-3 is now associated with the Western 
                                  Power Corridor (WESTCOR) and will be described 
                                  in detail later in this article. 
The Grand Inga scheme involves building a dam 
                                across the whole river so as to divert all the 
                                water into the adjacent Bundi valley, and the 
                                total flow rate of 26,400 cubic metres per second 
                                at its minimum can be used under a head of 150 
                                metres to generate 39,000MW in total (52 machines 
                                at 750MW each). 
                              
Export potential 
                              
Six power export corridors have been identified 
                                for power transmission from the Inga site as follows; 
                                western, northwestern, northern, northeastern, 
                                eastern, and southern (Figure 3). The existing 
                                Inga-Kolwezi HVDC and the AC network linking it 
                                to Zambia, Zimbabwe, Botswana, and South Africa 
                                forms the southeastern corridor. The western corridor 
                                will link Inga to West Africa, to supply the potentially 
                                large market in Nigeria, plus imports to the rest 
                                of West Africa. The northern and northwestern 
                                corridors will serve Morocco, Algeria, Tunisia 
                                and Libya. 
                              
Planned rehabilitation of Inga 
                              
Existing power stations 
                              
The characteristics of the existing power stations 
                                (Inga-1 and Inga-2) are given in Table 1. The 
                                Societé Nationale d' Electricité (SNEL) of the 
                                DRC owns and operates the two existing power stations, 
                                Inga-1 and Inga-2, with a combined output of 1,770MW. 
                              
Characteristics of the existing power stations 
                              
 
                              
                                 
                                 
                                  |  | Inga-1 | Inga-2 | 
                                 
                                  | Year of commissioning | 1972 | 1982 | 
                                 
                                  | Water head [metres] | 50 | 58 | 
                                 
                                  | Turbine flow [cubic metres per second] | 780 | 2,800 | 
                                 
                                  | Number of machines | 6 | 8 | 
                                 
                                  | Installed Capacity [MW] | 351 | 1,424 | 
                                 
                                  | Expected Production [TWh/Year] | 2.4 | 10.4 | 
                                
                              
                              Planned expansion 
                              
Inga-3 is the next phase of the development of 
                                the Inga site, with a projected output of 3,500MW. 
                                The final phase of the development will be the 
                                Grand Inga, with a potential rated output of 39,000 
                                MW. 
                              
Characteristics of the planned expansion 
                              
 
                              
                                 
                                 
                                  |  | Inga-3 (WESTCOR) | Grand Inga | 
                                 
                                  | Water head [m] | 6,300 | 26,400 | 
                                 
                                  | Turbine flow [cubic metres per second] | 50 | 58 | 
                                 
                                  | Number of machines [MW] | 3,500 | 39,000 | 
                                 
                                  | Expected Production [TWh/Year] | 23.5 | 288.0 | 
                                
                              
                              The western power corridor 
                              
The Western Power Corridor project (WESTCOR) 
                                is intended to exploit the environmentally friendly, 
                                renewable, hydroelectric energy of the Inga rapids 
                                site in the DRC. Load growth in the southern networks 
                                has outstripped expectations as a result of energy-intensive 
                                investments taking advantage of the excellent 
                                quality of supply available in the SADC region 
                                at internationally competitive prices. Studies 
                                have shown that additional generating capacity 
                                will need to be in regular commercial service 
                                in the southern networks of the SAPP by as early 
                                as 2007. 
                              
In addition, the Empresa Nacional De Electricidade 
                                (ENE) of Angola reported that the hydroelectric 
                                potential of the Cuanza Basin in northern Angola 
                                is approximately 6,000MW. ENE expressed interest 
                                in developing this resource and exporting the 
                                energy to WESTCOR and other customers in SAPP. 
                                An additional 2,500MW can be potentially captured 
                                from gas presently flared off in the northern 
                                Angolan oilfields. Elf Aquitaine and GEC Alsthom 
                                did a preliminary scoping study during the mid-1990s 
                                to export this available energy to South Africa. 
                              
The WESTCOR Joint Venture Company 
                              
The WESTCOR Steering Committee was formed under 
                                the auspices of the SAPP to initiate studies determining 
                                the viability of the Western Power Corridor with 
                                the source at Inga-3. The WESTCOR Joint Venture 
                                Company was registered in Botswana to fund the 
                                engineering and financial studies, and to build, 
                                own, and operate the infrastructure, should the 
                                project prove to be viable. Each of the five participating 
                                utilities contributed $100,000 as start-up capital 
                                to fund the first phase of development. 
                              
Five utilities are participating in the project. 
                                Each utility is represented on the Steering Committee 
                                and will own 20 per cent of the share capital 
                                of the proposed new joint venture company. The 
                                utilities are: 
                              
                                - NamPower, power utility company of Namibia 
                                
- Eskom, power utility company of South Africa 
                                
- Empresa Nacional De Electricidade (ENE), power 
                                  utility company of Angola 
                                
- Societé Nationale d' Electricité (SNEL), power 
                                  utility company of the DRC 
                                
- Botswana Power Corporation (BPC), power utility 
                                  company of Botswana. 
Environmental concerns 
                              
A complete Environmental Impact Assessment (EIA) 
                                study is scheduled in the immediate future for 
                                the twin HVDC lines serving as the interconnector 
                                through DRC, Angola, Namibia, Botswana and South 
                                Africa. Preliminary surveys, however, have not 
                                identified any evident environmental risks in 
                                the development of the project. Thus, it is anticipated 
                                that any environmental concerns found in the study 
                                will be easily resolved. Where the environmental 
                                impact of Inga-3 is concerned, the Congo river 
                                flow does not show seasonal variations to the 
                                extent of other rivers in the Southern African 
                                region, and is therefore sufficiently reliable 
                                to enable the Inga site to be developed on a run-of-river 
                                basis. The lack of variation in river flow is 
                                due to the catchments area that straddles the 
                                equator, and the seasonal rainfall patterns in 
                                the northern and southern areas that are contra 
                                cyclic to the river flow. This eliminates the 
                                need for a costly large storage dam to compensate 
                                for seasonal variations in river flow. In addition, 
                                eliminating the need to flood large areas significantly 
                                reduces the environmental impact. As a result, 
                                energy from Inga-3 would qualify as green energy 
                                in terms of the Kyoto Protocol on global warming, 
                                and the sale of carbon credits to developed countries 
                                could become an additional source of revenue for 
                                WESTCOR. 
                              
WESTCOR customers 
                              
The primary customers of WESTCOR are expected 
                                to be the SAPP member utilities. With Inga-3 producing 
                                3,500MW for WESTCOR, distribution along the transmission 
                                lines has been predicted according to the estimated 
                                demand within each of the five participating countries. 
                                Due to the cheap energy in Southern Africa the 
                                WESTCOR project will attract industry requiring 
                                high power consumption. Immediate examples are 
                                those of the Hindalco smelter, which will relocate 
                                from India to Walvis Bay in Namibia, as well as 
                                the Al smelter for BHP Billiton in Coega, South 
                                Africa. 
                              
This is a presentation by Mr. B. J. Mbuere 
                                ua Mbuere from Nampower and Dr. Lawrence Musaba 
                                from the SAPP Zimbabwe, presented at the Power 
                                Generation Conference