een wereldwijd elektriciteitsnet een oplossing voor veel problemen  GENI es una institución de investigación y educación-enfocada en la interconexión de rejillas de electricidad entre naciones.  ??????. ????????????????????????????????????  nous proposons la construction d’un réseau électrique reliant pays et continents basé sur les ressources renouvelables  Unser Planet ist mit einem enormen Potential an erneuerbaren Energiequellen - Da es heutzutage m` glich ist, Strom wirtschaftlich , können diese regenerativen Energiequellen einige der konventionellen betriebenen Kraftwerke ersetzen.  한국어/Korean  utilizando transmissores de alta potência em áreas remotas, e mudar a força via linha de transmissões de alta-voltagem, podemos alcançar 7000 quilómetros, conectando nações e continentes    
What's Geni? Endorsements Global Issues Library Policy Projects Support GENI
Add news to your site >>







About Us

Renewable Energy Law Alert: FERC Policy Statement Seeks to Accelerate Deployment of Smart Grid Technology

Jul 20, 2009 - Stoel Rives

On July 16, 2009, the Federal Energy Regulatory Commission ("FERC") issued its Policy Statement on smart grid technologies, directing the development of key operational standards and implementing an interim incentive rate policy that will allow for cost recovery of deployed smart grid technologies and certain legacy systems made obsolete by such deployment. The Policy Statement also establishes an important jurisdictional line by providing that, although FERC's rate recovery authority is limited by section 205 of the Federal Power Act, FERC is vested with the authority to adopt smart grid standards applicable to all electric power facilities—even those at the local distribution level and those directly used by retail consumers.

The Policy Statement identifies four grid functionalities that may serve to inform the Department of Energy's release of stimulus funds for smart grid projects. These functionalities are (1) wide-area situational awareness, i.e., the near real-time ability to view and react to interconnection-wide conditions; (2) demand response; (3) electric storage; and (4) electric transportation. FERC also stated that these functionalities are key to the development of future standards that will apply to smart grid technologies.

As stated above, the Policy Statement creates an interim rate policy with which FERC hopes to accelerate the implementation of smart grid technologies installed on the grid. Public utilities seeking assurance that they will recover smart grid costs must make a filing under section 205 of the Federal Power Act, or file an application for declaratory order, before FERC adopts smart grid interoperability standards. An applicant seeking cost recovery must make four demonstrations: (1) the smart grid facilities must advance the modernization of the nation's electricity transmission and distribution to securely and reliably meet future demand growth; (2) the deployed technology will maintain compliance with FERC-approved Reliability Standards such that grid cybersecurity will not be compromised; (3) the applicant has minimized the risk of stranded investment by relying on existing, widely-adopted interoperability standards and technologies that are readily and quickly upgradable; and (4) the applicant must share with the Department of Energy Smart Grid Clearinghouse the same information required by the Department of Energy for its grant program.

The Policy Statement establishes a number of incentive rate treatments that are meant to encourage the near-term deployment of smart grid technology, including pilot and demonstration projects. For example, a public utility applying for cost recovery will be allowed to undergo a single-issue ratemaking, meaning that the applicant need not reopen its entire rate base for FERC's review. A public utility may also use a single-issue rate proceeding to recover the costs of jurisdictional legacy systems being replaced by jurisdictional smart grid technologies. In addition, the interim rate policy allows rate treatments that provide for accelerated depreciation and abandonment authority, the latter of which may allow a public utility to recover the costs of certain abandoned smart grid projects.

If you would like to discuss the opportunities that are available as a result of FERC's Policy Statement, or if you have questions about smart grid funding opportunities available through the American Recovery and Reinvestment Act, please contact one of the following individuals. Click here for a copy of FERC's Policy Statement.

Seattle, Washington
Janet F. Jacobs at (206) 386-7582 or jfjacobs@stoel.com
J. Graham Noyes at (206) 689-7615 or jgnoyes@stoel.com
Geoff Revelle at (206) 689-8730 or ggrevelle@stoel.com
John Laney at (206) 386-7559 or jslaney@stoel.com

Portland, Oregon
Marcus Wood at (503) 294-9434 or mwood@stoel.com
Bill Holmes at (503) 294-9207 or whholmes@stoel.com
Dina Dubson at (503) 294-9675 or dmdubson@stoel.com
Jason Johns at (503) 294-9618 or jajohns@stoel.com

Minneapolis, Minnesota
Greg Jenner at (612) 373-8857 or gfjenner@stoel.com
Debra Frimerman at (612) 373-8819 or dhfrimerman@stoel.com

Sacramento, California
John McKinsey at (916) 319-4746 or jamckinsey@stoel.com
Lee Smith at (916) 319-4651 or lnsmith@stoel.com
Seth Hilton at (916) 319-4749 or sdhilton@stoel.com

San Diego, California
Brian Nese at (858) 794-4102 or bjnese@stoel.com

Boise, Idaho
John Eustermann at (208) 387-4218 or jmeustermann@stoel.com


OVER VIEW



Updated: 2003/07/28