
Abengoa steps up construction work
on Mojave Solar Project
Nov. 15 2011 - Chris Whitmore - pv-tech.org
Abengoa has begun ramping up construction on its
280MW CSP Mojave Solar Project after the California
Public Utilities Commission’s (CPUC) approved
its power purchase agreement (PPA) with Pacific Gas
and Electric (PG&E).
Now the regulator has given a green light to the
PPA, Abengoa can finally close financing on the US$1.2
billion federal loan it received from the Department
of Energy back in July. Although, despite only receiving
CPUC clearance on Thursday, preliminary work on the
1,765-acre site has been underway for several months,
with 81 workers already laying the foundations for
the pylons that will eventually hold the parabolic
CSP troughs.
Mojave is one of the few 100MW-plus projects in
the US to avoid getting bogged down in disputes with
environmental groups and labour unions. However,
reaching this stage has not been without difficulty.
Several leading figures within the CPUC have openly
campaigned against the development, claiming that
not only is the 25-year PPA uncompetitive, but the
solar trough technology used by Abengoa is outdated.
Nevertheless, by staying onside with the unions,
environmental groups and the California Energy Commission,
the Spanish developer has advanced the project to
the development stage.
“Abengoa has invested five years and about
US$70 million to get to the point where they are
ready to begin construction,” the CPUC’s
president, Michael Peevey, said. “To be rejected
by the CPUC would send a chilling message to the
business community, in my opinion.”
At present, Mojave has signed 24 contracts with
19 suppliers across six US states – 80% of
the equipment, supplies and services used by Abengoa
will be sourced in the US. Grid connection for the
whole 280MW is scheduled for spring 2014.
|