
First Solar Mesa construction site photo blog: The
next big PV production fab rises from the desert
Sep. 23, 2011 - Tom Cheyney - pv-tech.org
With
its framework structure erect and the first walls
attached, the shell of what will be one of the largest
PV manufacturing plants in the US is quickly rising
from the desert floor in Mesa, AZ, east of Phoenix.
The freeway-close First
Solar production center will
join the company’s mothership factory complex
in Perrysburg, OH, as a second domestic site once
it comes online next year. During a visit to—and
exciting Bobcat ride around—the project this
week, I found out that construction activities are
in full swing, as the accompanying photos attest.
The contractor team, led by global engineering and
construction firm M+W
Group, is building the nearly
million-square-foot, $300 million facility for First
Solar near the corner of East Elliot and South Signal
Butte roads on about 130 acres of what used to be
the GM/Mesa Proving Grounds, now owned by DMB.
Just off the perimter of the parcel, the chewed-up
asphalt remains of a former test track bear witness
to the site’s former life, although the rumbling
sounds now produced there emanate from earth movers,
cranes, water trucks, and other construction machinery.
Onsite sources told me that the initial facilities
equipment, such as piping, air compressors, and the
like, will start to show up by late October. The
building itself should be weather-tight by December,
with the first production gear rolling up in late
February and March. M+W expects to fulfill its contractual
purview and be off the site by the end of May.
Once the tools are installed by First Solar’s
equipment team, the first part of the ramp-up will
begin, with production expected to kick off in the
third quarter of 2012.
Although designed to accommodate as many as 10 production
lines, the thin-film company will start with a complement
of four cadmium-telluride moduling lines, currently
rated to produce a total capacity of just under 250MW,
in one segment of what will at first be a partially
fitted-out structure.
That number, however, is based on the firm’s
most recent reported run rate, which is a notoriously
fleeting target-metric. Almost every quarter for
the past several years, First Solar has continually
improved its manufacturing productivity and will
undoubtedly reach an even higher throughput level
when the fab begins producing modules.
Based on the latest historical year-to-year improvement
trends, the initial capacity/run-rate figure is more
likely to around 65MW or so per line, for a total
of 260MW.
Whether the company eventually installs the half-dozen
additional production lines at Mesa will depend on
demand and other market conditions. If it were to
do so in, say, Q2 or Q3 2013, the total capacity
for the 10-line factory, calculating for probable
run-rate improvements, would be approaching 700MW.
In addition to the main building, ground-mounted
PV test arrays will be positioned on separate locations
in the northeast, south, and southeast sides of the
property. There will also be a ~3MW CdTe rooftop
system providing some of the electricity for manufacturing
and administrative operations, similar to the one
installed at the Perrysburg site.
About 150 workers affiliated with the various contractors
and subcontractors are onsite now, but that number
will grow to at least 400 when construction begins
on the guts of the building and the equipment starts
to arrive. When the plant becomes operational, First
Solar estimates that it will employ 600 full-time
manufacturing associates there.
Once the new factory’s production line begins
processing glass in earnest, it will feed the increasingly
voracious appetite for modules of the company’s
2.6GW North American project pipeline, with most
locations within several hours’ to a half-day’s
tractor-trailer truck drive from Mesa.
As I observed first-hand earlier in the week, the
construction of one of those Utility-scale (note
the capital “U”) power plants—the
massive and impressive 290MW (AC) Agua Caliente project
near Dateland in Yuma County, AZ—is well under
way and should see the first few blocks of modules
(made in the company’s existing fabs) coming
online and sending energy to the grid by late 2011/early
2012.
(Editor's note: If you are reading this post on
a mobile device, may I suggest you check out our
complete PV-Tech site in order to view the accompanying
photos.)
|