
California regulator approves transmission
projects for wind power
March 28, 2007 Refocus.net
The California Public Utilities Commission
has approved two projects to construct transmission
to reach areas with high potential for green power
resources.
The regulator authorized Southern California Edison
to build the second and third segments of the Tehachapi
Renewable Transmission Project to facilitate delivery
of wind resources from windfarms in the Tehachapi
area and to prevent overloading of existing transmission
facilities. It previously determined there was a need
to construct transmission lines to Tehachapi to facilitate
the Renewables Portfolio Standard goal to have the
state's investor-owned utilities obtain 20% of their
power from renewables by 2010.
Earlier in March, the PUC approved construction of
SCE’s Antelope-Pardee transmission project in the
Tehachapi region, which was the first segment of the
project. Together, the three permits are worth US$1
billion of investment in California's energy infrastructure.
Tehachapi-Vincent includes a total of 56.8 miles
of new high-voltage lines and two new substations.
The PUC set a cost cap of $63 million for Segment
2 and $102.1 million for Segment 3; both segments
are projected to be in service by early 2010 and will
enable delivery of 700 MW of new wind generation from
Tehachapi.
Combined with the Antelope-Pardee line, the Tehachapi
Renewable Transmission Project will provide 4,500
MW of capacity from the Tehachapi resource area into
the Los Angeles Basin. SCE anticipates filing for
approval for eight more segments of the Tehachapi
project this summer.
The Final Environmental Impact Report for the transmission
project found “several significant environmental impacts
that cannot be mitigated” and “some impacts will remain
significant even after the implementation of mitigation,”
the decision notes. “Upon balancing the substantial
economic, operational, legal, technological, social
and other benefits of the proposed Tehachapi-Vincent
Transmission Project against the unavoidable environmental
impacts, we find that the project should be approved
with the conditions contained in this decision.”
The EIR identified an environmentally superior alternative
that differs from SCE’s proposal, but the PUC approved
the project as proposed by SCE, rather than the environmentally-preferred
alternative.
|