 |
Utility Grid-Connected Distributed Power Systems
National Solar Energy Conference
ASES Solar 96
Asheville, NC
April 1996
Donald E. Osborn/David E. Collier
Sacramento Municipal Utility District
6301 S Street: MS# A401
Sacramento, CA 95817 USA
ABSTRACT
The utility grid-connected market has been
identified as a key market to be developed to
accelerate the commercialization of photovoltaics.
The Sacramento Municipal Utility District (SMUD)
has completed the first three years of a continuing
commercialization effort based on the sustained,
orderly development of the grid-connected, utility
PV market. This program is aimed at developing
the experience needed to successfully integrate
PV as distributed generation into the utility
system and to stimulate the collaborative processes
needed to accelerate the cost-reductions necessary
for PV to be cost-effective in these applications
by about the year 2000. In the first three years,
SMUD has installed over 340 residential and
commercial building, grid-connected, rooftop,
"PV Pioneer" systems totaling over 1.4MW of
capacity and five substation sited, grid-support
PV systems totaling 860 kW bringing the SMUD
distributed PV power system to nearly 5 MW.
SMUD also established a partnership with its
customers through the PV Pioneer "green pricing"
program to advance PV commercialization and
to develop rooftops as "PV power plant" distributed
generation sites.
1. INTRODUCTION
The Sacramento Municipal Utility District
(SMUD) is the fifth largest public utility in
the nation and serves a 900 square mile area
in and near Sacramento County, California. SMUD
plans to have at least half of its energy obtained
from energy efficiency and renewable resources
by the year 2000. Solar energy will provide
an important part of both the "DSM/Energy Efficiency
Power Plant" and renewable energy, distributed
generation resource. Investments made in solar
power today are expected to provide the customer-owners
of SMUD with substantial long-term energy and
community benefits.
The SMUD Solar Program has three elements designed
to increase Sacramento's use of solar energy.
The Solar Domestic Hot Water Program uses attractive
performance based rebates and financing and
strict quality assurance requirements to encourage
the electric water heat customer to switch to
solar water heating. Since May 1992, over 3000
SMUD customers have used this program and reduced
their electric water heating energy consumption
by an average of 60% and provided the District
with needed peak capacity and energy benefits.
The Solar Buildings Program provides design
assistance and incentives to encourage the incorporation
of cost-effective passive and other solar features
in the design and construction of both new buildings
and the retrofit of existing buildings. The
Solar Buildings Program is also responsible
for collaborative solar cooling development
and demonstration projects.
The Solar Electric Program includes solar thermal
electric systems, such as the Solar Two Central
Receiver Project and the Utility-scale Solar
Dish/Stirling Engine Joint Venture, and a wide
variety of photovoltaics applications aimed
at the accelerated commercialization of grid-connected
PV systems.
2. SMUD PV PROGRAM
SMUD has embarked on an ambitious commercialization
effort based on the sustained, orderly development
of the grid-connected, utility PV market. This
program is aimed at developing the experiential
base needed to successfully integrate PV as
distributed generation into the utility system
and to stimulate the collaborative processes
needed to accelerate the cost-reductions necessary
for PV applications to be cost-effective in
these applications.
SMUD is playing a leadership role in the commercialization
of grid-connected PV through its own PV programs
as well as helping to developing the collaborative
State and national utility PV commercialization
efforts underway including the Utility Photovoltaic
Group (UPVG) and Photovoltaic for Utilities
(PV4U) programs.
SMUD is a leader in utility grid-connected applications
of PVs with the world's largest distributed
PV power system. The SMUD PV system, currently
nearly 5 MW, includes SMUD PV1/PV2 (2 MW operating
since 1984, figure 1), the first public PV electric
vehicle recharge station in the West, residential
grid-connected PV installations, and numerous
remote power and sensor applications including
a number of PV powered street lights and PV
powered, emergency phones. In 1993 SMUD adopted
a long-term PV commercialization strategy aimed
at accelerating the cost-reduction of grid-connected
utility PV applications.
Figure 1. SMUD's 2 MW PV generating station
at site of the closed Rancho Seco nuclear
plant. Established 1984.
As part of this effort SMUD installed in 1993
716 kW of grid-connected PV systems. These systems
include 109 4 kW (400 kW total) residential,
roof-mounted PV systems; a 30 kW commercial
building sited, concentrating PV system; and
a 258 kW substation sited, distribution support
PV system. The 1994 SMUD PV Program included
889 kW of grid-connected PV systems. These included
400 kW of residential rooftop, 144 kW of commercial
rooftop, a 3 kW demonstration building integrated,
PV roofing system and 3 substation projects
totaling 342 kW. The 1995 SMUD PV Program included
845 kW. These included 416 kW of residential
rooftop systems, a 263 kW substation system
and two PV parking lot systems (166 kW).
Both the 1994 and the 1995 PV Projects include
USDOE/UPVG TEAM-UP cost-share funding. The 1995
additions will bring the SMUD Distributed PV
System to nearly 5 MW (Table 1).
2.1 Rating of PV Systems
SMUD has adopted a convention of rating the
effective kW output of grid-connected PV systems
based on national utility standards. All PV
systems, unless otherwise noted, are rated based
on the AC output of the system at PVUSA test
conditions (kW, AC, PTC). PVUSA Test Conditions
(PTC) are used by the utility industry and specified
by UPVG. PTC ratings are typically 10% more
conservative than the Standard Test Conditions
(STC) ratings used by the PV industry.
To account for the differences in energy production
between fixed and tracking PV systems, the Energy
Production Factor, EPF, has been adopted. Established
by the Utility Photovoltaic Group (UPVG), the
EPF factor permits a more appropriate comparison
between fixed and tracking systems. This permits
the conventional comparison of $/W to attach
value to the additional energy production value
of tracking as well as accounting for the added
cost. SMUD rates tracking PV systems based on
the AC output of the system at PVUSA test conditions
with the Energy Production Factor adjusting
the nominal output of the system (kW, AC, PTC,
EPF).
Table 1: SMUD PV Projects through 1995
| 1980s: 2460
kW,EPF |
Rancho Seco PV1:
1000kW (1230kW.EPF) |
Arco System (1984)
Rancho Seco PV2: 1000kW (1230kW.EPF) |
Arco/Solarex/Mobil
(86) |
|
|
|
| 1993: 716 kW,EPF |
PV Pioneers 93:
400kW, 108 3-4kW Siemens Systems (1993-94) |
Hedge PV1: 210kW
(258kW,EPF) UPG/Siemens System (1993-94) |
SMUD Warehouse
PV: 30kW (37kW,EPF) SEA System (1993-96) |
PVEV Charging
Station: 11kW Arco System (1992) |
PV Res Demo Systems:
10kW Various (1992-93) |
|
| 1994: 889kW,EPF |
PV Pioneers 94:
400kW, 119 3-4kW Solec Systems (1994-95) |
PV Pioneers Commercial
94: 144kW, 8 10-30kW Solec (1994-95) |
Hedge PV2: 108kW
APS System (1994-95) |
Hedge PV3: 102kW
RMI/Solarex System (1994-95) |
Hedge PV4: 107kW
(132kW,EPF) UPG/Siemens System (1994-95) |
WAPA BI-Roof Demo:
3kW (1994) |
| 1995: 845kW,EPF |
PV Pioneers 94/95:
87kW, 25 3-4kW RMI/Solarex Systems (1994-95) |
PV Pioneers 95:
329kW, 80 3-4kW Placer/Solarex Systems (1995-96) |
Rancho Seco PV3:
214kW (263kW,EPF) UPG/Siemens (1995-96) |
PVEV Airport:
8kW Arco System (1995-96) |
PV Solar Carport:
128kW (158kW,EPF) UPG/Siemens (1995-96) |
|
| Total PV on
system: 4.9MW,EPF (4.3MW, Nominal) |
2.2 Residential PV Pioneer Project
The 1993 SMUD PV Pioneer Project established
a partnership with customers willing to assist
in the early adoption of photovoltaic (PV) technology.
Under the PV Pioneer Program, SMUD purchases,
installs, owns, and operates 100+ residential
rooftop PV systems, each about 4 kW, each year
(Figure 2 and 3). SMUD plans to continue adding
at least 100 PV Pioneer systems each year for
5 years.
Figure 2. SMUD Residential PV Pioneer (System).
SMUD customers (the PV Pioneers) volunteer
to share in this effort through a form of "green
pricing" and by providing the roof area to place
the environmentally friendly, solar electric
generation PV systems. The PV Pioneer pays a
$4 per month premium (about 10 to 15% of the
average electric bill) on their utility bill
to participate. In doing so, the PV Pioneers
have the satisfaction of generating clean, renewable
energy on their own rooftops. SMUD gains experience
in the installation, operation, maintenance,
pricing strategies and other aspects of residential
PV systems and obtains low-cost "power plant
sites." This joint effort also helps accelerate
the commercialization of PV as part of a process
of sustained, orderly development.
The 1993 PV Pioneer systems were supplied as
108 turn-key, installed systems totaling 400
kW by Siemens Solar Industries (SSI) for $7.70/W
AC, PTC. The 4 kW systems make up a standard
400 square foot array. A few systems were down-sized
to accommodate homes with smaller roof area.
Innovative roofjacks permitted quick installation
of the PV array. The complete PV system installation
requires only half of a day. The PV system parallels
on the utility side of residential service meters
and enters the utility grid through a separate
utility meter mounted next to the house utility
meter.
The 1994 PV Pioneer systems were supplied by
Solec International, Inc. as 109 3.7 kW systems
with Omnion invertors at a turn-key cost of
$6.23/W.
The 1995 PV Pioneer Program included Resource
Management International and Solarex supplying
25 3.5 kW systems with Pacific invertors contracted
for in 1994 at a turn-key cost of $6.98/W. An
additional 80 4.1 kW systems (329 kW) from Placer/RMI/Solarex
using Trace invertors at a turn-key cost of
$5.98/W were contracted for in 1995. These systems
were installed on residential and commercial
rooftops in late 1995 and early 1996.
Figure 3. Installation of PV Pioneer System
2.3 Customer Attitudes and Response to PV
Green Pricing
It is up to local communities, states, the
utilities and the public at-large to take the
lead in demanding and providing the extensive
use of solar energy. A March 1993 scientific
market research survey showed that the people
of Sacramento are interested in helping to lead
the way to a cleaner, sustainable future. The
following survey results demonstrated the willingness
of SMUD customers to support "green pricing"
programs for PV.
Willing to pay a premium price (15%) for PV
generated electricity from their rooftops: 26%
of the general, and 57% of the "green" population.
Willing to pay a premium (15%) with rate stabilization
of the PV portion: 49% of the general, and 77%
"green" population.
Willing to participate in a general "green pricing"
program of 1 to 10% of the utility bill to for
a "Clean Energy" program District wide (not
necessarily on their own roof): 70% of the general,
and 88% "green" population.
The customer response to the PV Pioneer Program
has greatly exceeded expectations with about
1000 customers volunteering each year. Of these,
about 600 pass the pre-qualifying screen and
agree to pay the PV Green Fee premium. From
this pool, the 100+ PV Pioneers for each year
are selected. With the restrictive roof requirements,
qualifying rooftops have been a much greater
constraint to volunteers than the "green fee".
2.4 Commercial Building Sited PV Systems
This project provides for the installation
of PV Pioneer systems on commercial rooftops.
The first system, started in 1993 and completed
in 1995, is a nominal 30 kW, single axis tracking,
concentrating PV system uniquely adaptable to
roof-top applications installed on the SMUD
59th Street Warehouse. This tracking system
has an effective rating of 37 kW, EPF. The system
by Solar Energy Applications Corp. (SEA), is
a roof mounted single axis tracking, concentrating
PV system with a south orientation at a 38 degree
pitch. The system uses 10X concentration fresnel
lenses focused on the PV cells and covers 4000
square feet of roof area. The system price of
this demonstration project is $7.41/watt, EPF.
The 1994 SMUD PV Program installed in 1994 and
1995 flat plate PV Pioneer systems on commercial
building roof-tops totaling 144 kW by Solec
for $6.25/W. These Commercial PV Pioneers include
a 24 kW system on a VFW Hall and a 30 kW system
on the Wilton Bible Church (figure 4) and five
additional systems of various sizes installed
on church roofs. Each requires about 100 square
feet of roof area for each kW.
Figure 4. 30 kW Wilton Bible Church Commercial
PV Pioneer System.
2.5 Building Integrated and Parking Lot Sited
PV Systems
The 1994 PV Program installed a 3 kW building
integrated PV demonstration system in partnership
with the Western Area Power Administration (WAPA,
Figure 5). The PV system is integrated in the
reroofing structure installed on a WAPA office
building. The PV roofing tile system is part
of the roofing system installed to insulate
and protect the roof membrane. The "Powerguard"
PV system in being designed and installed by
Powerlight Corporation and Western Single Ply,
a commercial roofing contractor. A full size,
40 kW system is scheduled for installation in
1996 on another WAPA building.
Figure 5. SMUD/WAPA Building Integrated 3
kW PV Roofing System
Solar Design Associates and
Solarex are scheduled to complete in early 1996
a demonstration of an AC PV Module system. The
AC PV module incorporate the invertor as part
of the PV module. This permits the PV system
to be built up an AC building blocks. Two residential
PV Pioneer systems are being completed with
these AC PV modules. This demonstration is part
of a DOE PVBONUS supported project.
In 1994, the lowest bid received by SMUD for
a parking lot sited PV system was for nearly
$10/W. While the development of parking lot
air space for PV energy production is of very
high priority to SMUD (and especially important
in urban/suburban areas) the price was too high.
In 1995 Utility Power Group bid a 158 kW, EPF
parking lot sited PV system. This system is
a single axis tracking system and costs $6.36/W,
EPF. The installation at Sacramento Municipal
Airport is scheduled for completion in Spring
of 1996. A smaller 8 kW parking lot system was
also installed at the airport site.
2.6 Substation Sited, T&D PV Systems
The 1993 project installed a 258 kW, EPF (210
kW nominal) ground mount, single axis tracking
PV system at the SMUD Hedge Substation. The
installation of this PV system demonstrated
the ability and versatility of placing medium
size PV systems for District distributed generation
benefits. The system is located at the Hedge
Transmission and Distribution training yard
and connected to the 12kV distribution system.
The system was designed and installed by Utility
Power Group (UPG) and is a single axis tracking
258 kW, EPF PV generation plant. SMUD provided
the site preparation and utility grid interconnection.
The turn-key system price was $7.70/watt (nominal)
compared to $8.90/watt for the PG&E 500kW
Kermin PV plant completed in Spring 1993. The
system (figure 6) is a ground mount, flat plate,
single axis tracking system utilizing Siemens
solar modules. A 250 kW Omnion inverter/transformer
converts 720 VDC to 12.47 kVAC for grid interconnection.
Accounting for the increased production due
to tracking (using the Energy Production Factor,
EPF) the effective price was $6.26/W AC,EPF.
The system was completed in early 1994.
Figure 6. 210 kW SMUD Hedge Substation PV
system.
Three additional PV power
stations at the Hedge site totaling an additional
317 kW were installed under the 1994 program
and completed in 1995. Bell Products, Inc. and
Advanced Photovoltaic Systems, Inc. supplied
a fixed, 108 kW system using the APS thin-film
module and a Kenetech invertor at a cost of
$6.68/W. Resource Management International and
Solarex supplied a fixed, 102 kW system using
Solarex modules and a Kenetech invertor at a
cost of $7.35/W. Utility Power Group and Siemens
Solar supplied a 132 kW, EPF (107 kW nominal)
single axis tracking system using Siemens modules
and multiple UPG invertors at a cost of $7.50/W,
nominal or $6.10/W EPF.
The 1995 substation PV project is a 263 kW,
EPF (214 kW nominal) single axis tracking system
by Utility Power Group. This system has a turn-key
price of $5.71/W, EPF ($7/W nominal) and is
scheduled for completion Spring 1996.
2.7 1993 - 1995 SMUD PV Program Cost Improvements
The 1994 SMUD PV Program systems showed substantial
cost improvements over the 1993 projects. This
improvement has continued into 1995. This is
true both for the turn-key contract costs as
well as for the costs incurred by the utility
to develop, procure, administer, and perform
the Utility side of the systems installation
and integration into the grid, as can be seen
in the following table for the residential (RES)
and substation (SUB) systems.
1993 - 1995 SMUD PV COST IMPROVEMENT
TURN-KEY SMUD4 TOTAL 30 yr
| PROJECT-YR |
COST1 |
ADD COST |
COST |
/kWh5,6 |
| SUB - 19932 |
$6.26/W |
$3.89/W |
$10.15/W |
32 |
| SUB - 19943 |
$6.68/W |
$1.07/W |
$ 7.75/W |
21 |
| SUB - 19942 |
$6.10/W |
$0.87/W |
$ 6.97/W |
19 |
| SUB - 19952 |
$5.71/W |
$0.91/W |
$ 6.62/W |
18 |
| RES - 19933 |
$7.70/W |
$1.08/W |
$ 8.78/W |
23 |
| RES - 19943 |
$6.23/W |
$0.90/W |
$ 7.13/W |
20 |
| RES - 19953 |
$5.98/W |
$0.89/W |
$ 6.87/W |
18 |
- Turn-key contract cost up to utility interconnection
without tax, bonding or utility add-on costs.
- Single axis tracking system. Includes credit
for Energy Production Factor (EPF) [for single-axis
tracking, EPF = 1.23 compared to fixed tilt].
- Fixed, non-tracking system, EPF = 1.00
- Includes: interconnections, metering, site
preparation, District labor, administration,
overheads, tax, bonding, AFUDC, and other
costs.
- Includes: O&M, does not include DOE
cost-share.
- Preliminary estimate.
2.8 The Roof-top Resource
In metropolitan areas, hundreds of thousands
of square acres of residential and commercial
roof area, parking lots and transmission corridors
are setting unused in the sun. As Skip Fralick
of San Diego Gas & Electric Company pointed
out, "This rooftop area is the equivalent
of "free land" for photovoltaic generation:
it needs no development, environmental impact
statements, or extensions of transmission
lines." In Sacramento alone, these south to
west oriented roofs, parking lots and transmission
corridors represents the potential of hundreds
of megawatts of photovoltaic resource.
Power plant siting is normally a troublesome,
time consuming and expensive exercise, especially
in a suburban or urban area. However, over
the past three years, SMUD has sited about
340 PV power plants all across Sacramento
with little trouble or expense. Indeed, hundreds
of customers have paid extra on their utility
bill to host a SMUD PV power plant on their
roof. This ease of siting combined with the
environmental, modular and distributed benefits
of PV add substantially to the value PV brings
to the utility's energy mix.
3. A UTILITY PERSPECTIVE ON PV COMMERCIALIZATION
There is a critical need to accelerate and
complete commercialization of PVs to meet
our needs for grid-connected, utility applications
for year 2000 and beyond. Without a concerted
and collaborative effort we can not assume
that PVs will be ready to serve the utility
market when we will need it. Our actions today
are our investments for tomorrow.
The off-grid, "currently cost-effective" PV
applications are not sufficient to commercialize
and make cost-effective the grid-connected,
utility PV applications. We must continue
the process of the grid-connected market development
directly. These grid-connected applications
have value beyond energy and capacity and
include residential and commercial customer
sited PV for distributed generation and DSM
applications and substation/T&D sited
PV for grid-support value.
There are three central concepts necessary
to achieve the production levels and cost
reductions required for the accelerated commercialization
of photovoltaics for utility systems:
- Sustained Orderly Development (SOD)
- Commercialization path life-cycle costing
- Proactive leadership to stimulate early
adoption
3.1 Sustained Orderly Development
(SOD)
The solar industry needs a reliable and longterm
market volume to develop and achieve longterm
cost reductions required for full commercialization.
Current "costeffective" utility markets have
not provided sufficient market volume to accelerate
commercialization. Demonstration and R&D
projects alone do not accelerate the commercialization
of new technologies. In fact, large, one-time
purchases tend to dry up supply (and thereby
increase price) without stimulating the increase
in production capacity necessary for manufacturing
cost reductions. Furthermore, manufacturers
do not rely upon short term subsidies, mandated
purchases, or set-asides in making investment
decisions because these programs create "false
markets." A combination of aggressive price
reductions and commitments for substantial and
sustained capacity acquisition is required for
full commercialization of these technologies.
Sustained orderly development and economies
of volume for solar electric systems will result
in the rapid development of a mature, costeffective
solar industry.
3.2 Commercialization Path LifeCycle Costing
Technology development (or commercialization
path) lifecycle costing, and not just "project"
lifecycling costing, needs to be used. It is
important to analyze total expenditures and
total acquired capacity over the entire commercialization
path. Higher costs for early applications can
be a good investment if they contribute to accelerating
the trend towards lower costs and higher performance.
When solar investments are selected carefully
and in collaboration with other stakeholders
in renewable energy development, they can be
among the wisest and, ultimately, the lowest
risk investment that can be made, despite their
higher initial capital costs.
3.3 Proactive Leadership to Stimulate Early
Adoption
Sustained orderly development and accelerated
commercialization will not occur early relying
just on natural market forces. Accelerated commercialization
will not occur just by demonstration projects
and watching the cost curve. Utilities and other
potential bulk purchasers must commit to an
early and sustained series of substantial buys
to permit the industry to invest in expanded
production and automation. The "diffusion model"
of PV commercialization where high value applications
are identified and filled, then the next value
level developed is an important starting point.
It does not, however, result in a sufficient
aggregation of order commitments to allow the
needed expansion of production. The utility
grid-connected market needs to foster accelerated
commercialization with multiyear commitments
for substantial and continuing, multimegawatt
per year purchases.
While these early increments of PV may not be
cost effective on their own, they represent
a beginning of a cost effective process. Support
by the other stakeholders in the process, especially
by other utilities, the regulators and a reliable
DOE shared risk is required on a sustained,
multi-year basis to close the early cost-value
gap and make the process work. This support,
can not be on a year-to-year, stop and go basis.
It must be match the multi-year commitment that
the utility industry is making. The utility
community has taken the responsibility to get
this process underway now and to work with regulators,
customers and other stakeholders to make it
successful. The national Utility PV Group (UPVG,
now up to 90 utility members) has implemented
the first projects under TEAM-UP. Project TEAM-UP,
provides the initial part of a sustained, orderly
development process with a target of 50 MW of
utility PV purchases over a four year period.
Under this proposal the USDOE would provide
only about 30% of the estimated $513 million
program. As Andrew Vesey, Chairman of the UPVG
Board of Directors and Vice President of Niagara
Mohawk Power Corporation stated:
While TEAM-UP's partners may greatly help
to underwrite today's "cost gap", only the federal
government can close it. Critically, this federal
support must also be sustained. Funding
assurance is essential for gaining market and
supplier commitments, gearing up and implementing
the program, verifying the march down the cost
curve, and establishing the federal government
as a reliable partner throughout the entire
commercialization process.
The successful, accelerated commercialization
of utility PV applications will need to be a
collaborative effort of many participants. Utilities,
State and Federal agencies and other stakeholders
must join together. If manufacturers do not
continue to respond with aggressive forward
pricing, if utilities do not implement substantial,
sustained purchases, if DOE does not provide
a reliable and predictable multi-year costshare
absorbing a part of the early risk and if other
stakeholders do not proactively support the
commercialization process, this process won't
succeed.
4. PV COMMERCIALIZATION COST CURVE
Photovoltaics (PV) offer many advantages as
distributed generation systems, both as a supply
side option and as a demand-side management
(DSM) option. PV's are the most modular and
operationally simple of the clean, distributed
power technologies. From 1972 to early 1992,
PV module costs have been reduced 100-fold.
Already PV is a cost-effective resource for
a wide variety of remote and grid-independent
applications. The strategic, competitive advantages
of PVs will continue to increase as this cost
trend continues.
Despite tremendous price decreases, PV is still
too costly for most grid-connected applications.
In addition, cost-effective storage and the
related problem of intermittency of the solar
generated electricity continue to limit PV utility
applications.
Significant RD&D efforts are underway nationally
to develop more efficient batteries and other
electricity storage methods that will help to
resolve the storage and intermittency problems.
The problem of cost is being attacked on several
fronts. New PV materials and designs are being
developed to improve efficiency and reduce manufacturing
costs and niche markets are being developed
and exploited to continue the initial phases
of commercialization. Indeed, the current level
of production capability is all but sold out
for remote applications, consumer devices and
third world applications.
To achieve the next series of price reductions,
firm utility scale markets must be generated
and sustained to encourage the investments needed
in new technology and production. Utilities
can play a leading role in accelerating the
further commercialization of PVs through assisting
the development of utility PV markets. This
effort can reap benefits for our customers by
the resulting improvements in PV systems, distributed
generation support to our system and accelerated
reductions in PV costs.
Residential "rooftop" systems in the 2 to 4
kW range were costing about $15/W installed
in 1992. Substation applications were costing
about $10/W. The SMUD 1993 PV projects cost
about $7.70/W and for the 1994 PV projects averaged
about $6.44/W with a low of $6.10/W. The 1995
projects, despite constrained PV module supplies,
have continued tracking down the accelerated
commercialization cost curve with prices as
low as $5.71. With a sustained, widespread collaborative
effort, one could expect prices to drop below
$3/W by about the turn of the century. Figure
7 summarizes SMUD's analysis of the TEAM-UP
commercialization plan. It shows the expected
results of a sustained orderly development process
on the utility PV market based on a number of
market studies by the PV industry, analysis
by SMUD, UPVG and others and from sources from
DOE and the national labs.
In 1993 SMUD implemented its commitment to a
sustained orderly development effort starting
with the 640 kW of grid-connected utility PV
systems and a 5 year program of yearly PV Pioneer
and T&D buys. This 5 year program leads
to a 5 year period starting in 1998 where SMUD
will purchase about 10 MW per year of renewable
energy resources including PV. It is expected
that this multi-year effort would involve the
establishment of a new PV manufacturing facility
with part of it's production dedicated to the
multi-year, multi-megawatt utility commitment.
This is especially important since it is generally
agreed that "ramping up" to commercial scale
PV production for utility applications cannot
be at few kilowatts at a time, but rather in
annual sales in the multi-megawatt range. These
orders need to have continuity and be steadily
increasing. Early utility industry orders and
PV production increases need to be in the range
of 2-5 MW/year, and they must quickly (within
2-3 years) reach 10 MW/year and 50-100 MW/year
nationwide by the end of this decade. While
the efforts of a few utilities, such as SMUD,
can achieve some initial reductions of price,
the needed cost reductions for commercialization
will require a much broader effort. The level
of response to the 1995 TEAM-UP program is indicative
that this level of commercialization can be
maintained given only modest - but sustained
- DOE shared-risk. These efforts, supported
by all the stakeholders in the PV commercialization
process, will be necessary if PVs are to achieve
the cost reductions needed to meet our needs
in a reasonable time-frame.
Figure 7. SMUD PV SOD Commercialization
Cost-curve
Sustained Orderly Development (SOD) assumes
fully implemented, sustained TEAM-UP commercialization
effort.
Prices ($/W) are Turn-key system prices up
to meter, AC, PTC, 30 year life. Includes installation
and tax. Does not include Utility Add-on Costs.
Real 1994 $.
Year 2000 Cost-effectiveness range based
on: SMUD Gas Fired Generation (GFG) to Lower
Bound Renewables (LBR) Year 2000 costs. Fixed,
Rooftop PV systems. Tracking systems adjusted
by Energy Production Factor (EPF). Turn-key
system prices (total project cost less Utility
Add-on Costs). Does not include non-traditional
benefits such as Distributed Benefits.
5. SMUD'S CONTINUING SOD PV PROGRAM
During 1996, the District will continue its
efforts to accelerate the commercialization
of grid-connected PV applications and to define
and compare the relative costs and benefits
of the various models of utility PV applications
including the issues of systems ownership, shared
risk and benefits, levels of T&D benefits
and the general issue of the appropriate accounting
for all the value of distributed generation.
This information will be used to update the
analysis of PV benefit/cost as part of the integrated
planning process.
In Spring 1996, SMUD will release its multi-year
Request for Proposals for Renewables (RFP4R).
This RFP4R plans to obtain 50 MW of renewable
energy resource over a 5 year period, 1998 -2002.
As part of this solicitation, a 10 MW PV set-aside
has been included. Proposals are expected that
will provide for PV systems that will continue
the SMUD PV Program, meet or exceed the cost
goals indicated by the cost curve in figure
7 and result in significant PV and PV related
manufacturing and jobs in the Sacramento region.
Proposals are expected to be due to SMUD in
the summer of 1996 and SMUD expects to sign
contracts in early 1997.
6. COLLABORATIVE PV COMMERCIALIZATION
To succeed in accelerating the commercialization
of grid-connected utility PV applications, the
commercialization process must truly be a collaborative
effort. The PV industry needs to nurture the
grid-connected, utility market. They need to
aggressively forward price to foster this developing
market and to enable utilities to field systems.
They need to look at investing in this market
development now to create a profitable market
for the future. Utilities need to proactively
assist in developing a substantial, growing
and sustainable grid-connected utility PV market.
They need to aggressively account for the non-traditional
benefits of distributed PV generation and maximize
what they can afford to invest in early systems
to accelerate the cost reduction and commercialization
of grid-connected PV. Regulators need to recognize
that the long term best interests of the ratepayer
will be served by permitting and encouraging
modest early investments in higher cost PV today
when these investments will lead to earlier
and greater cost reductions of PV for the future.
They need to account for societal and economic
development benefits and the benefit of commercializing
a source of "green and inflation-proof" energy.
The Federal government needs to share the risk
by helping to fill the cost-value gap, a gap
declining as commercialization moves forward,
between how high utilities and regulators can
value PV benefits and how low the PV industry
can forward price grid-connected PV systems.
The Federal government must show that it can
be a reliable, sustained partner and not jerk
support up and down as the winds of the political
moment shift back and forth.
Each party needs to analyze their investment
for a "commercialization-path" life cycle cost
rather than a project-by-project basis. This
process must be developed as a sustainable,
orderly development of the market in a way that
the PV industry can invest with confidence in
new processes and manufacturing lines to lower
costs and that utilities and their regulators
can see accelerated and continuous progress
to cost-effectiveness.
Efforts such as the Utility PhotoVoltaic Group's
Project TEAM-UP with the USDOE and the PV4U
collaborative state working groups offer the
framework to make this collaborative commercialization
of the grid-connected, utility PV market succeed.
As was stated in Time Magazine of October 18,
1993:
Some of the biggest boosters of solar power
are bound to be utility companies, eager for
a clean source of electricity that will enable
them to produce more power without new billion-dollar
plants. Both as consumers of solar technology
and as the promoters of home solar panels, utilities
will drive much of the industry's growth into
the next century. "Utilities are beginning to
realize that they're going to have to get on
the solar bandwagon, says S. David Freeman,
(former) general manager of the Sacramento Municipal
Utility District (SMUD). "If they don't and
rates go up sharply, people are going to buy
their own solar panels and pull the plug on
the utilities." ... "Solar is competitive now
if you take the long view. And it's going to
be highly competitive by the end of the decade."
The use of solar energy has many benefits to
utilities, the our local communities and the
country in general. Solar technology reduces
the use of non-renewable resources. It is a
renewable and sustainable energy source and
helps improve air quality. PV power generation
systems are clean, quiet and environmentally
beneficial. They use no fuel and have no emissions.
Each MW of PV power generated by a plant with
a 25% capacity factor, will eliminate the production
of more than 20,000 tons of carbon dioxide and
more than 25 tons of NOx during its life as
compared to the cleanest fossil fuel plants
available for purchase today. Solar electric
systems stimulate economic development and employment
opportunities to a much greater extent than
conventional energy sources. They represent
a source of diversified, inflation-proof energy.
For all these reasons, PV represents an energy
supply that utility customers are demanding.
The question is, do we have the national will
to make a modest but sustained commitment to
the investment in our future that will make
this a cost-effective and substantial part of
our national energy mix in the timeframe that
we need.
National Solar Energy Conference, ASES Solar
96,
Asheville, NC, April 1996
Questions? Contact the Green Power Webmaster
This page Most Recently Updated August 9,
2000
DOE
| EREN
| NREL
|