
Huge network needed to export power
Sept. 29, 2011 - drukgreen.bt
It will require 1,460km of additional transmission
lines
An important aspect of the government’s target
to harness 10,000 megawatts of hydroelectricity by
2020 is to export surplus power to India. This will
need building a huge network of transmission lines
that is projected to cost between Nu 50-60B. According
to projections by the energy department, total generation
by 2020 will be around 11,488MW. By then, peak domestic
demand, which is less than 300MW today, is expected
to be around 1,500MW if the economy grows at the
same rate. The remaining 9,988MW will be exported
to India. The department of energy has worked out
a national transmission grid master plan to provide
a road map of building transmission lines and substations
for export of surplus hydropower to India once the
ten projects under the 10,000MW initiative become
operational. Pooling stations in India and Bhutan
will also have to be identified to transmit power
to the load centres in India. The Indian government
will finance the additional 1,460km of transmission
lines for the ten projects to export power. As of
now, Bhutan has 1,007km of high voltage transmission
lines built for Tala, Chukha, Basochu and Kurichu.
But these transmission lines are built individually,
without any holistic national plan. The energy department,
in consultation with the central electricity authority
of India, is preparing the master plan. Preparing
the master plan in itself is expected to cost about
Nu 18M.The master plan project, implemented in January
2010, is in its final stages, and will be completed
by December this year. The plan will also serve as
a road map beyond 2020 if or when new projects are
to be built. The executive engineer of DoE, Karma
Tshewang, said the national grid master plan was
felt necessary to ensure minimum environment impact,
and the difficulty of getting right of way to build
thousands of kilometres of transmission lines. “The
master plan will basically be a holistic approach,
which will guide the Bhutan Power Corporation and
new projects in building transmission lines from
the projects to the Indian border, after which it
will be connected to the Indian towers,” he
added.The transmission lines will have to be built
by the projects themselves up to the Indian border."We
want to avoid a crisscross of transmission lines
across the nation,” Karma Tshewang said. “The
master plan will provide directions as to how and
where to build the lines DoE will be organising a
workshop by October end in Paro, where India’s
central electricity authority officials will be presenting
the final draft of the master plan to Bhutan’s
electricity sector, the national environment commission,
land commission and forestry department. The first
project to build transmission lines based on the
master plan will be the Mangdechu project, which
has 720MW installed capacity, the construction of
which began this year, and will be completed first
after Punatshangchu I and II.
|