
The Economic,
Environmental and Developmental Benefits of High-Voltage
Interconnections Between South and North America
via Central America and the Caribbean
Michael Hesse Wolfe, International
Energy Planning Consultant, USA
Peter Donalek, Hrza Engineering Company, USA
Peter Meisen, Global Energy Network Institute, USA
ENERLAC 93
Bogota, Colombia
June 15 - 18, 1993
1. SUMMARY
This
paper addresses the potential for expanding current
efforts to complete power system interconnections
in Central America towards an Inter-American Transmission
System (IATS), that would interconnect northern South
America with North America via Central America and
the Caribbean. The principal reason for expansion
of the concepts for interconnection would be to emphasize
the greater utilization of renewable resources by
deliberately creating an export trade in energy derived
mainly from major sources of renewable hydropower
in South America. The energy would be delivered initially
to the countries of Central America and Mexico from
sources in Colombia and Venezuela, and eventually
with Brazil, Ecuador and Peru. The initial transmission
system envisaged is a hybrid, comprising a three-terminal
high voltage direct current (HVDC) system between
a converter terminal in Colombia and an inverter terminal
in Mexico, connected mid-isthmus to an a.c. Central
American Interconnected System via a HVDC tap-station.
Eventually this hybrid system could be expanded to
include terminals in Brazil, Ecuador and Venezuela
connected to additional bipoles to Mexico and a marine
cable system to Florida via the Antilles in the Caribbean.
Emphasis is given to an initial program for firming
of existing generation and transmission capability
in Central America, to be followed by a planned expansion
of generating capacity in source countries with transmission
interconnection facilities extending from South to
North America via Central America and the Caribbean.
Staged
expansion of the interconnection would enable considerable
regional economic and environmental benefits to be
realized. The principal economic advantages of interconnection
are rationalization of investment in new generation
and transmission facilities, coupled with improvements
to operating flexibility and efficiency, resulting
in reductions to cost of supply. To these would be
added new revenue resulting from export of surplus
energy derived from renewable resources and consequent
environmental benefits resulting from the displacement
of fossil-fired thermal generation. A regional environmental
development compact (EDC), which would place these
benefits in a regional perspective, could provide
the political framework for cooperation by regional
participants. It is envisaged that there would be
a positive role for OLADE and ECLAC in support of
CEAC and other regional participants to the EDC. Also
addressed is the financial support necessary from
the World Bank and regional banks, IDB and BCEI, together
with a suggestion for conversion of existing commercial
debt to local currency components of investment in
generation and transmission facilities. In this way
an initial economic boost is given to national economies
by debt conversion to be followed by progress towards
economic growth and integration.
There
is momentum towards hemispheric economic integration
in the Americas, provided by several regional economic
areas, or common markets, at different levels of development,
from nascent political formation to legislative process
[1]. These regional economic groupings
are part of the present pattern of convergence towards
evolved forms of integrated economic areas. The global
economy tends to encourage this convergence, with
participation at different levels by regional trading
blocs. One feature of this convergence is the supportive
role played by energy exchange made possible by regional
power system interconnections.
In
South, Central America and North America, four subregional
economic groupings have been formed or are being actively
pursued. These are natural groupings evolving in geographical
contiguity and economic affinity. Andean countries
along the Cordilleras Blancas began the process of
economic market formation under the terms of the Andean
Pact but, due to adverse economic circumstances, convergence
to meaningful integration has been slow. Argentina,
Brazil, Paraguay, and Uruguay formed MERCOSUR in the
southern cone but progress towards integration is
also slow. In the countries of Central America, some
progress was made to form a Central American Common
Market but efforts have languished due to conflict
situations in the isthmus area over the past decade.
At the present time, efforts are being made to revive
hopes for Central American integration. Possibly the
best example of positive progress in the hemisphere
is the expansion of NAFTA to include Mexico together
with Canada and the United States. This can be expected
to provide an example of what can be achieved with
regional economic integration in North America. The
example will surely cause re-examination of the basis
for further progress with economic common markets
in Central and South America. A precedent is thus
set for forward movement in other subregions of the
Americas, one feature of which would be extension
of power system interconnections to facilitate intra-regional
energy exchange.
In
the progress towards economic integration of common
market areas, energy could be defined in terms of
its role as a leading sector. As we near the year
2000, the impact of energy on the global environment
is more certain of critical review than in past decades.
The unique advantage of energy as a catalyst to economic
integration in the Americas is that renewable energy
resources such as hydropower exist in abundance in
countries of South America, whilst they are already
well developed in North America. The possibility of
energy transfer based upon this renewable resource
development imbalance is then a factor that could
contribute to economic integration between South and
North America, via Central America and the Caribbean.
2. Renewable Energy and Interconnection
for Economic Growth
The
potential of renewable energy development to spur
economic growth and integration of common markets
is two-fold. Firstly, it would provide energy for
local industrial and commercial growth requirements,
contributing to domestic and, through trade expansion,
regional economic growth and market integration. Secondly,
if energy export from renewable resources were to
be introduced on a sufficiently large-scale, revenue
from export sales would contribute to local and regional
development as well as preservation of the regional
environment. This could only be made possible by extended
power system interconnections.
At
first, renewable energy would contribute to reduced
consumption of fossil fuels, which would reduce both
foreign exchange requirements for those countries
having to import petroleum or coal and the environmental
impact of fossil fuel combustion on air quality in
urban areas. As subregional interconnection is extended,
these benefits are also provided to wider areas. An
example of this would be the proposed interconnection
between Machala in Ecuador to Tumbes in Peru to enable
surplus hydropower from the Paute Project to replace
thermal generation in Tumbes [2a].
The first stage is modest: A seasonal range of power
between 5 and 8 MW to be exported over a 69 kV line,
but nevertheless the savings are tangible in terms
of both the cost of alternative generation and relative
environmental impact.
As
more ambitious interconnections are completed, economic
andenvironmental effects are magnified. Once the second
stageinterconnection between Machala and Tumbes is
completed, 30 MW of transfer capacity will be available
between Ecuador and Peru. Interconnection capacity
will be further increased in this border area by the
Puyango-Tumbes binational project. In the northern
Andean zone, a ten-fold increase in transfer capacity
is projected for the 300 MW capacity 230 kV interconnection
between Venezuela and Colombia, to link San Mateo
and El Corozo via a 50 km transmission line through
the Andes [2a].
Also
in the Andean zone, plans for interconnections between
Ecuador and Colombia are under implementation which
will eventually enable reliable, economic energy exchange
between the central systems of both countries, taking
full advantage of seasonal hydroelectric generation
diversity between the Amazon and Pacific basins [2a].
This emphasizes the considerable benefits that are
associated with major system interconnections, which
certainly contribute to economic growth of subregional
participants. Greater utilization of hydropower also
enhances environmental benefits from development of
renewable resources.
Along
the Atlantic coast of northern South America, prefeasibility
studies have been made by the governments of Venezuela
and Guyana to determine the relative economic advantages
of an interconnection between two hydropower projects
on the Lower Caroni in Venezuela and the Guyana electric
power system. Delivery of power would be made from
the future Macagua II and Tumeremo stations, which
would be interconnected by a 200 km section of 400
kV line in Venezuela, to a terminal at Linden in Guyana
over a 400 km section of 200 kV line.
Benefit/cost
analyses indicate that this export of power from Venezuela
would enable Guyana to realize significant fuel cost
savings and avoid possible energy rationing [2a].
In this case, development of dedicated hydropower
generation for export would be possible, enabling
Venezuela to earn revenue from renewable energy resources
and Guyana to displace the need for costly fossil
fuel generation. Mutuality of interest is then possible,
which would lay the basis for future expansion of
dedicated generation for export of electrical energy
converted from renewable resources.
One
such future market for hydropower in reasonable proximity
to northern South America is the subregional grouping
of countries in Central America. The intent to form
a Central American Common Market has been aided by
the extension of transmission interconnections between
countries along the isthmus. Apart from Belize, the
other six nations of Guatemala, El Salvador, Honduras,
Nicaragua, Costa Rica and Panama are sequential links
in the chain of countries from Mexico in southern
North America to Colombia in northern South America.
In 1991, only a 230 kV transmission link between Honduras
and El Salvador remained to be built to complete interconnection
between all six electrical power systems of Central
America [2b]. The natural extension
to this formation would be a southern interconnection
between Panama and Colombia to be followed by a northern
link between Guatemala and the central interconnected
system of Mexico. As capital formation for generation
expansion in Central America is partially reliant
on private sources, most new generating plants are
relatively small and their output tends to be absorbed
immediately by local demand after commissioning. Seasonal
hydropower, such as from run-of-river plants in Costa
Rica, enable whatever surplus energy is available
periodically to be exported via existing interconnections.
The present need is to firm supply capacity in the
six countries taking into consideration the limited
surplus available for export. Future reinforcement
of transmission capacity should be planned in context
of the need to optimize on shared generation capacity
via interconnecting links. There are several medium
size hydropower sites available for development: Boruca
in Costa Rica and Copalar in Nicaragua [2b].
The output of these could be shared following a sequential
building program that would enable investment capital
to be allocated with an efficient disbursement schedule.
These larger plants, in the order of 300 MW capacity,
could be developed on a joint basis together with
associated transmission interconnections. However,
during the period of generation and transmission capacity
firming, it would be appropriate to evaluate the feasibility
of extending transmission from Panama to Colombia
for interchange of surplus hydropower. Alternatively,
dedicated hydropower could be developed in Colombia
and Venezuela for export to Mexico via Central America.
In this case, it would be essential to fully evaluate
the relative technical and economic merits of EHV
AC or HVDC as a preferred transmission mode. At some
juncture, the purpose of the Inter-American transmission
system would change from a normal mode of energy interchange
between national systems to also include delivery
of power over a long-distance interconnection from
Colombia to the natural regional demand center, Mexico
City. At this stage it is likely that a hybrid system
would be required, comprising a three-terminal HVDC
system from Columbia to Mexico City, with a tap-station
in Central America to the underlying interconnected
a.c. system on the isthmus.
In
the 2lst century, it may be possible to further expand
hydropower exports from South America to North America
by building dedicated HVDC transmission systems from
terminals in Colombia, northwestern Brazil, Ecuador
and Venezuela to three energy centers on the border
between Mexico and the southern United States [3].
The energy centers would be developed within the context
of NAFTA, primarily for renewable energy export to
the U.S. and termination of the Inter-American transmission
system. These energy centers would serve to buffer
flows of power northwards to the NERC regions of WSCC,
ERCOT and SPP. This would complete the interconnection
of South America with North America. Its transfer
capacity could then be gradually increased, as required,
according to demand growth in relation to economic
sources of renewable energy supply. In addition, if
feasible, a marine cable interconnection could be
made from Venezuela to Florida via the Antilles in
the Caribbean. The map in Figure I shows the general
location of interconnection terminals and overland/undersea
routes for the Inter-American Transmission System.
Figure I
Inter-American Interconnection Terminals
and Corridors
3. Natural Convergence of Regional
Needs and Potentials
Over
the last decade, many countries in the region have
undergone domestic political turmoil, civil strife
and foreign intervention. United Nations population
trends predict 50% more people in the region in the
next 25 years, most preferring urban areas. [4]
Both the people and the environment of the region
are suffering as a result, with widespread poverty
still being the norm for millions of Latin Americans.
The
benefits of electrical energy: clean water, refrigeration
of food and medicine, waste disposal, communications;
are available to only the wealthier minorities in
each country. Lack of electricity can be easily correlated
with high rates of infant mortality, as well as high
birth rates. [5] A priority of sufficient
electric power for all should be a social commitment
made by all leaders of the region.
3.1 Regional Environmental Needs
and Renewable Energy
All
developing countries are dedicated to improving the
standard of living for its citizens. Yet protecting
the environment in the process of development is often
forgotten. Burning wood for cooking and heating supplies
the immediate needs of survival, but clears forested
lands more quickly than they are replanted. The "cleaner"
power technologies that are now available are usually
more costly than the budgets of the nations can afford,
and proprietary interests often keep new technology
out of reach.
The
great opportunity of the Mexico to Colombia-Venezuela
region is vast potential of renewable energy. Hydro,
geothermal, wind and solar energy are abundant beyond
the actual energy needs of the region. Along with
high voltage power transmission, these sources can
be tapped for domestic development, and the excess
used for export. These energy sales will have two
major benefits: first, to return income for national
development programs and debt repayment, second, to
displace the more polluting fuels with cheaper electricity
from non-polluting renewable sources.
3.2 Potential of Renewable Energy
as a Catalyst for Growth
By
working in concert, the Latin American countries could
interest both technical expertise and foreign investment
into the region. This investment into primary infrastructure,
will bring jobs in construction, operation and maintenance
of power transmission and control centers. More importantly,
this integration of electrical infrastructure will
help bring the economies of Latin America into a more
competitive world standing. New markets will naturally
open as the region's economic situation recovers.
4. Role of Intra-Regional Power
System Interconnections
Interconnection
of power systems within the region serves as a tangible
sign of the economic integration of national economies
into logical sub-regional market areas. International
power flows over transmission systems represent another
form of trade, with electrical energy being the basic
exchange commodity. However, intra-regional power
transmission interconnections are made in response
to definite technical, economic and financial criteria.
These criteria are discussed below in relation to
proposed regional interconnections.
4.1 Economic Operation of Interconnected
Power Systems
The
usual motive for interconnection is to improve the
economic operation of generation and transmission
systems, as they expand to form more viable territorial
extensions. Improvements to operation include the
ability to utilize generation on a more rational basis
for energy generation. Thermal unit operating efficiencies
and cost of fuel are taken into consideration by economic
dispatch and variations in hydrologic cycles are compensated
for in the case of hydropower. Reliability of supply
is improved as the number of generating units are
increased through interconnection of supply areas.
Firm power and economic energy may be exchanged to
suit the operating requirements of interconnected
supply systems.
4.2 Optimization of Capacity and
Transmission Expansion
Advantages
that may be gained from interconnection are associated
with overall system expansion, including the timing
of capacity additions which are key to financial investment.
When a system is entirely self-reliant, more capacity
has to be built to satisfy demand and reserve margin
requirements. Interconnection enables sharing of capacity
additions over time, which results in postponement
of system additions. The cost of generating plant
and transmission interconnections may be shared by
adjacent utilities, such that investment in generation
and transmission facilities to individual participants
is minimized or deferred. Optimization of supply networks
enables power demand to be met with a minimum of new
generating capacity additions and transmission extensions
for interconnected system expansion.
4.3 Rationalization of International
Investment Programs
In
this time of budgetary restraint, system interconnections
allows rationalization of international investment
programs. Capital is used efficiently as minimal outlays
are possible with least cost expansion programs. Optimization
of supply facilities over the expansion period enables
capital plant additions to be postponed, or sometimes
canceled, which results in reductions to capital disbursements
through time. In addition, power system interconnection
is being given new emphasis with increasing international
environmental awareness. Stack emissions are reduced
whenever thermal plants are postponed or canceled,
which would be a positive consideration by international
and regional financial institutions such as the World
Bank and Inter-American Development Bank.
4.4 Interconnection of Energy Sources
to Distant Markets
In
addition to advantages resulting from local system
interconnection, it is now possible to contemplate
regional interconnections between major sources of
renewable energy to distant demand centers. Advances
in transmission technology allow delivery of large
capacity blocks of power and energy over very long
distances, from remote sources to distant markets.
Transmission corridors up to 7,000 kilometers are
within the extended range of high voltage d.c. (HVDC)
and it is therefore possible to think in terms of
continental distances for HVDC transmission reach
[6]. Thus, remote renewable energy
sources that would not be developed near-term to satisfy
local demand can be thought of as potential sources
of supply for distant markets, particularly if alternative
generation sources are mainly fossil. The imperatives
of environmental development suggest that one of the
principal ways to counter global warming and regional
pollution from fossil combustion would be to include
more renewable energy sources in the supply mix. Interconnection
of remote renewable energy sources to distant markets
for displacement of fossil generation would be one
way in which a major impact could be made on sources
of environmental pollution.
4.5 Potential for Export of Surplus
or Dedicated Energy
In
Central and South America there is great potential
for export of renewable energy, either surplus to
local requirements or as a dedicated supply for energy
export. Abundant hydro resources exist in northern
South America and both hydro and geothermal resources
exist, along the Isthmus of Central America. It is
entirely conceivable to deliver hydropower from Colombia
to Mexico via the countries of Central America. It
is also possible to think in terms of a more inclusive
system of interconnection to link hydropower sources
in Colombia, Brazil, Ecuador, and Venezuela with North
America via overland transmission systems through
Central America and by a combination of marine cables
and island transmission systems across the Caribbean.
However, it is necessary to carefully plan the staged
interconnections through time, with close coordination
by participating nations within the region.
4.6 Integration of Systems to Maximize
Economic Growth
With
long-term maximization of economic growth as an objective,
it is necessary to think in terms of steadily approaching
the goal, within a well coordinated master plan to
integrate existing plans for system interconnection
along the Isthmus of Central America with extensions
to North and South America. Extension of the interconnection
between Guatemala, El Salvador, Honduras, Nicaragua,
Costa Rica and Panama will be necessary to link major
sources in Colombia, Brazil, Ecuador and Venezuela
with Mexico and the United States. Basically, what
could be accomplished through time would be intra-regional
interconnection of power systems that would build
on existing interconnected networks within the Andean,
Central American, and NAFTA market areas embracing
Mexico and certain US-NERC regions.
5. Regional Distribution of Power-Energy
Demand Centers
The
main power and energy demand centers under consideration
for assessment of the potential for future interconnection
of South and North America via Central America and
the Caribbean are Mexico City and the capital cities
of Central American countries, assuming that a limited
number of taps would be made to transmission systems
comprising the Inter-American Transmission System
(IATS). It is further assumed that power delivered
to demand centers would be available to supply a portion
of country loads via interconnected national transmission
systems. In order to approximate the relative distribution
of power along the transmission system, total national
demand projections are given in Table
1.
Table 1:
Diversified Demand for Mexico and
Countries of Central America
(Megawatts)
| |
1980
|
1984
|
1989
|
1995
|
2000
|
| Mexico **1 |
|
|
17,340
|
25,250
|
34,300
|
|
|
|
|
|
|
| Guatemala |
330
|
500
|
850
|
1,500
|
2,400
|
| El Salvador |
340
|
500
|
750
|
1,200
|
1,800
|
| Honduras |
160
|
270
|
440
|
800
|
1,300
|
| Nicaragua |
270
|
390
|
610
|
860
|
1,400
|
| Costa Rica |
450
|
630
|
990
|
1,700
|
2,600
|
| Panama |
400
|
500
|
990
|
2,000
|
3,500
|
| Total **2 |
1,700
|
2,600
|
4,200
|
7,300
|
11,700
|
Sources:
**1/
1989 Forecast of Comision Federal de Electricidad
(CFE)
**2/
Central America Power Interconnection: A Case Study
in Integrated Planning, World Bank Energy Department
Paper No. 15, April 1984
It
may be observed that the Central American country
loads are of a similar order of magnitude and that
their total diversified demand is approximately 1/4
of the total diversified demand for Mexico in 1989,
ranging up to 1/3 in 2000. The load growth of Mexico
is increasing at a faster rate than that of the six
Central American countries, indicative of the stagnation
in Central America. However, in relation to the justification
for interconnection, Mexican load growth offers a
definite incentive to eventually supply the CFE system
mix with electrical energy from hydropower sources
of northern South America.
The
primary factor which would govern the economic transfer
of power to Central America and Mexico would be the
amount of power relative to installed capacity and
the delivered cost of energy in relation to prevailing
energy tariffs. The 1988 values given in Table
2 are indicative of respective levels in the countries
of Central America.
Table 2:
Countries of Central America (1988)
|
|
Installed Capacity
|
Energy Sales
|
Cost of Energy
|
Average Tariff
|
|
|
MW
|
GWh
|
U.S. cents/KWh
|
U.S. cents/KWh
|
|
Guatemala
|
741
|
1,835
|
3.8
|
6.1
|
|
El Salvador
|
651
|
1,662
|
2.5
|
4.3
|
|
Honduras
|
561
|
1,352
|
4.9
|
8.5
|
|
Nicaragua
|
333
|
952
|
2.6
|
5.0
|
|
Costa Rica
|
852
|
2,935
|
2.8
|
4.8
|
|
Panama
|
879
|
1,974
|
6.8
|
11.2
|
Source:
The
Evolution, Situation and Prospects of the Electric
Power Sector in the Latin American and Caribbean Countries,
World Bank Infrastructure and Energy Division and
the Latin American Energy Organization (OLADE), 1988
The
spread between actual cost of energy and average tariff
suggests that there is a reasonable margin for negotiation
between energy suppliers and purchasers within the
upper limit of average tariffs for retail sales of
energy. However, it indicates how the economics of
interconnection are dependent upon relative marginal
cost levels for energy generated and delivered from
remote sources compared with that of potential energy
purchasers. Transmission energy losses over long interconnections
will be a determining factor in negotiations.
6. Resource Centers of South and
Central America
The
principal resource centers of northern South America
are located in the countries of Colombia, Brazil,
Ecuador and Venezuela. Of these, only the northwestern
area of Brazil is considered for hydropower development
dedicated to export and Ecuador is regarded as being
a suitable center for delivery of surplus hydropower
from other Andean countries to the south, such as
Peru.
6.1 Characterization of Resource
Base for Interconnection
The
principal resource that is considered suitable for
energy export is large capacity hydropower. Other
renewable resources, such as small to medium capacity
hydro and geothermal in Central America are suitable
mainly for local supply or, if surplus to local demand,
could supply equivalent energy to partially compensate
for transmission losses in the interconnection system.
The environmental impact of large hydropower developments
has caused serious questions to be raised whenever
potential high-head sites are considered for development.
However, hydro resources are still relatively benign
when compared with combustion of coal and oil for
energy generation. Stringent environmental assessment
criteria have been introduced by the World Bank and
other institutions. These criteria and rigorous assessment
procedures will help screen candidate sites to remove
potential problematical developments from further
consideration. One other possibility is a turn towards
large capacity low-head developments that rely more
on dynamic flow rather than potential head for energy
conversion. Innovative designs for prefabricated modules
with caisson-mounted bulb units would be suitable
for river transport logistics rather than ecologically
disruptive roads and dam construction in areas such
as Amazonia. This technique may well provide a valid
alternative to high dams and large reservoirs, and
is worthy of detailed investigation.
6.2 Regional Sites of Major Renewable
Energy Resources
Hydropower
sites being considered are concentrated in the northern
part of South America. A low-head development at Ilha
Grande on the Rio Negro in Brazil is a potential source
of hydropower that could be developed for export,
as sites along this tributary of the Amazon are far
from major Brazilian load centers and the rainforest
of Amazonia is unsuitable for construction of transmission
systems. However, the relative proximity of Ilha Grande
to the highlands of Colombia would provide a natural
route for transmission dedicated to power export as
the terrain would be more suitable for transmission
corridors.
6.3 Major Renewable Energy Resource
Center Locations
In
addition to Ilha Grande in Brazil, other hydropower
sites in northern South America are located in Colombia,
Ecuador, Peru and Venezuela, the Magdalena basin in
Columbia, the western slopes of the Andes in Ecuador
and Peru, together with the Orinoco-Caroni basins
in Venezuela are the location of major hydropower
resources. These could be considered the renewable
energy resource centers that would provide the bases
for major hydropower developments. An indication of
the relative magnitude of hydropower resources is
given in Table 3.
Table 3
Hydropower Resources of Northern
South American Countries
|
Hydraulic Conditions
|
Colombia
|
Ecuador
|
Peru
|
Venezuela
|
|
A..Average annual flow:
|
|
|
|
|
|
Generating capacity - MW
|
50,000
|
21,000
|
12,500
|
11,600
|
|
Energy generation - GWh/yr.
|
300,000
|
126,000
|
109,200
|
98,000
|
|
B. Maximum usable 95% of
year:
|
|
|
|
|
|
Generating capacity - MW
|
3,200
|
1,200
|
3,800
|
7,500
|
|
Energy generation - GWh/yr.
|
25,900
|
9,600
|
30,700
|
60,100
|
Source:
World
Energy Conference survey data
Colombia
has the largest hydropower resource base, approximately
half of the combined total of 95,100 MW generating
capacity for average annual flow conditions. The relative
magnitude of hydropower resources in Central America
may be compared by reference to Table
4. The total for the six countries of Central
America is approximately 18 percent, or 17,200 MW.
Table 4
Hydropower Resources of Central American
Countries
|
Hydraulic Conditions
|
Guatemala
|
El Salvador
|
Honduras
|
Nicaragua
|
Costa Rica
|
Panama
|
| A. Average Annual flow |
|
|
|
|
| Generating capacity - MW |
1,176
|
900
|
4,800
|
3,600
|
4,326
|
2,400
|
| Energy generation - GWh/yr. |
5,880
|
4,500
|
24,000
|
18,000
|
37,898
|
12,000
|
| B. Maximum usable
95% of year: |
|
|
|
|
| Generating capacity - MW |
472
|
180
|
840
|
660
|
840
|
420
|
| Energy generation - GWh/yr. |
3,778
|
1,440
|
6,720
|
5,280
|
6,720
|
3,360
|
Source:
World
Energy Conference survey data
There
is the possibility of future supply to Central America
and Mexico from surplus hydropower in northern South
America. Staged development of an Inter-American Transmission
System is required to gradually evolve an interconnection
between renewable energy sources and demand centers.
The map of Figure I indicates power flows from main
resource centers to Mexico over four main interconnections,
three overland routes and one undersea and island
route:
- Ilha
Grande, Brazil to Mexico via Central America
- Colombia
to Mexico via Central America
- Ecuador
to Mexico via Central America
- Venezuela
to Florida via Caribbean islands
It
is assumed that HVDC would be the preferred transmission
mode, both for overland bipole routes through Central
America and for the marine cables and cross-island
bipole route across the Caribbean. Limited d.c. tap
terminations would enable island power in-feeds to
supplement local supply and diminish reliance on diesel-engine
generating units.
6.4 Location of Transmission Interconnection
Terminals
Ecuador
could be the site of a HVDC converter terminal that
would transmit surplus power from the Andean subregion,
embracing hydropower sites in Ecuador and Peru. These
sites would be interconnected by an extended EHV AC
system superimposed on existing local high voltage
systems. Colombian hydro sites would be served by
a separate HVDC converter terminal, as would sites
in Venezuela. Due to geographic disposition, the three
terminals in Colombia, Brazil and Ecuador would be
interconnected with Mexico via the Isthmus of Central
America, while the terminal in Venezuela would be
more suitable for interconnection to Florida by HVDC
marine cable systems via the Caribbean island chain
of the Antilles. This would probably be the last interconnection
to be implemented due to the relative cost of marine
cables compared to overland HVDC bipoles.
6.5 Potential Integration of Renewable Energy Centers
Integration
of renewable energy centers will require a coordinated
program to develop hydropower resources in the countries
of northern South America. Initial steps to interconnect
sources and systems within this subregion are proceeding.
To build on the many possibilities for future interconnection
will need cooperation between the several national
power authorities to formulate a plan for staged development
of subregional hydropower sources and transmission
systems to establish priorities and schedule design
and construction programs.
7. Firming of South and Central American Power
Systems
The countries
of Central America have basic electric transmission
and distribution systems. These have been developed
over the years as part of each country's needs. In
many cases the development was based on the demand
for electricity in the large metropolitan areas. In
more recent times the electrification system was part
of plans to electrify the country and may have been
part of larger plans to industrialize and modernize.
The development
of electric power systems from localized systems serving
large cities and urban centers to the construction
of nation wide bulk power systems began in the late
1940's. Following 1945 several countries embarked
on plans to modernize. Among the accoutrements of
a modern nation were a national airline, a hydro electric
station and electric transmission lines. Computer
based central dispatch and high speed communications
systems followed.
The bulk
power and generation facilities one finds throughout
Central America today provide the basis for the next
evolutionary step in the development of a regional
electric power system. In the past decade, each country
has installed some form of central load dispatch (Energy
Management System). Such facilities are an essential
facility to the control of system operation.
A compelling
force driving the development of a regional electric
power transmission system is the realization that
a quantum step is required to assure a secure energy
future for the region. This is coupled with the need
for sufficient and reliable supply of electric energy
is basic to any plan for modern development.
Although
existing bulk power transmission systems are sufficient
in most cases for national interests, the need for
an interconnected regional system imposes a more rigorous
set of criteria. Existing transmission systems must
be developed in two ways. One in the direction of
a common high voltage that allows power and energy
interchange between systems and second is the need
to firm existing capacity and transmission within
each region.
Transmission
within each country must be firmed up so that the
effects of a unit outage or loss of a heavily loaded
line do not result in a major disturbance that would
jeopardize the flow of power and energy on the regional
interconnection. The reliability of the overall regional
interconnection will impose a new reality constraint
on each system in the region. This restriction will
be that each system must be as self sufficient as
it possibly can. This can also be stated in terms
of reliability by stating that any system disturbance
within a system shall not have a negative impact on
a neighboring system.
Long range
benefits to participating countries will follow from
interconnected system operation as a result of the
creation of a new major electric utility market. The
total electrical load accessible from the interconnected
systems will be of sufficient magnitude to justify
large generation projects. These can be geothermal
and hydro electric projects in the 1,000 MW range.
There will probably also be some natural gas and oil
fueled plants required for operating and control requirements.
In 1992
several countries in the region suffered a drought.
The direct impact to the electric energy sector is
reduced output from hydro electric plants. Since there
are inadequate transmission interconnections, it is
not possible for the drought stricken countries to
import electric energy from neighboring countries.
This situation has focused attention of energy planners
and policy makers in the region on the importance
of interconnected utility operation.
7.2 Existing Transmission Systems and Interconnections
Since
the 197O's several interconnections have been constructed
between the countries of the region, These are:
|
Countries
|
Design
Voltage - kV
|
|
El
Salvador - Guatemala
|
230
|
|
Honduras
- Nicaragua
|
230
|
|
Nicaragua
- Costa Rica
|
230
|
|
Venezuela
- Columbia
|
230
|
|
Mexico
- California
|
230
|
|
Mexico
- Texas
|
115
and 138
|
Each of
the six Central American countries have 230 kV as
their highest established transmission voltage. At
the terminal ends of a HVDC system, the highest established
voltages are: Mexico - 400 kV, Colombia - 500 kV,
and Venezuela - 745 kV.
The country
of Belize is a special case in that it is separated
from the existing transmission systems in the region
by a large undeveloped area. In addition to the separation
it has a relatively smaller load. Thus the combination
of small load magnitude and distance makes Belize
difficult to include in present plans for interconnection.
In addition
to the systems on the main land bridge between the
south and north continents there is the case of the
island systems along the archipelago from Trinidad
to Florida. These systems, although not connected
with transmission lines, do have an organizational
interconnection. The island systems belong to the
Caribbean Electric Utility Services Corporation (CARILAC).
Through their combined common interests they can act
as an electric utility group, and would be able to
participate in future plans for underwater cable connections.
7.3 Planned System Extensions and Proposed Linkages
The idea
of interconnecting the power systems in the countries
of the region is not new. The idea has been discussed
and considered previously. In the early 1970's the
Commission Economica Para America Latina (CEPAL) commissioned
a study of the interconnection of the Central American
utilities. The report developed a transmission interconnection
plan based on a 400 kV alternating current backbone
transmission system, and underlying 230 kV national
systems.
The CEPAL
plan was based on a principle that power and energy
exchange between countries would allow the sequential
development of large generating facilities on a country
by country basis. It envisioned the need to accommodate
the express transfer of power and energy through the
region as a long term goal.
With the
major electrical market created by the interconnection
it will be possible to construct large hydro and geothermal
projects that were not previously economically viable.
There are several large hydro projects in Central
America that were feasible as engineering projects
but not economically feasible because available native
load was too small relative to the plant capacity.
A general rule of system planning is that total installed
capacity in one plant site should not be more than
25% of system peak demand. When the Central American
region has a transmission interconnection, then these
projects will become viable because total interconnected
load will be sufficiently greater than the plant capacity.
The CEPAL
plan has value in the present discussion. It provides
the basis for route selection, and identifies locations
in each country where connections can be made to the
existing bulk power transmission system. In some cases
the connection point is selected in anticipation of
the development of a large hydro generation plant.
Many concepts of the CEPAL plan remain valuable today,
and others require review. Most importantly the CEPAL
study served to keep the concept of regional interconnection
in view.
The CEPAL
study also provides the basis for the need to construct
national and regional energy management centers. These
are necessary to control and account for the reliable
and uniform interchange of power and energy between
parties. From a technical perspective one needs to
control system frequency, voltage and real and reactive
power flow within each system and across the interconnection
points between systems. From a commercial point of
view a regional control center will be required to
monitor and record power interchanges between systems,
and for the purpose of allocating costs for power
and energy transactions.
7.4 Priority Areas for Firm Capacity and Transmission
Each country
has specific needs and problems to consider with regard
to transmission requirements. With the advent of the
proposed region wide transmission system concept,
each country will be required to examine internal
needs and plans for expansion with regard to electric
power. This review will involve preparation of load
forecasts, population trends, industrial and agricultural
developments, transportation systems and other unique
issues. As these data are developed they will be used
by decision makers confronted with the task of deciding
how their system will fit into the regional transmission
system.
8. Staged Extension of Intra-Regional Interconnections
8.1 Regional Program for Staged Power System Expansion
Present
interconnections require review and study to determine
if in their present configuration they are adequate
to meet the needs of intra regional interconnections.
This can be done using load flow and transient stability
planning software tools. The objective of such an
effort could be to formulate a long range interconnected
transmission system. The capacity and reliability
of the interconnections would be analyzed and studied
to determine how the system responds to various contingency
and basic operating contingencies.
Based
on the results of system performance studies a revised
plan can be identified. The plan should conform to
some predetermined system performance criteria. It
is a suggestion that a minimum set of system performance
criteria be established. The criteria would cover
such items as: amount of spinning reserve, transmission
outage criteria, frequency and voltage regulation
requirements, as well as generation and transmission
planning criteria.
8.2 Intra-Regional Program for Staged Interconnections
From an
engineering perspective the accomplishment of a staged
interconnection within Central America can be considered
to be underway. There are no technical engineering
barriers to interconnection. What is required however
is a regional mind set be established in which there
is the political will and desire to accomplish such
a plan because it has a common sense basis.
This may
be a difficult hurdle to overcome since it requires
agreements between electric utility organizations
as well as agreements between sovereign nations. There
are however examples of how this can be achieved,
and it is expected that under the relentless and persistent
force of economic necessity and need for reliable
energy supply that a program of staged interconnection
will be established.
8.3 Defined Stages for Extension of System Integration
The stages
for system integration are driven by several issues.
These are: reserve sharing, desire to construct large
hydro and geothermal projects, revenue from the sale
of electric energy, and related water storage and
irrigation issues.
When forecasts
for future electricity demand and energy are prepared
and matched with other needs of the region, it should
become apparent that a fundamental key in the long
range future of the region is a reliable and economical
supply of electric energy. With the schedule of need
and economic growth firmly established, the development
sequence for the interconnected electric system will
be known.
8.4 Definition of System Control and Energy Management
Electric
Utility Organizations throughout Central America have
recognized that there is an economic advantage if
they can interchange electric energy. Technical personnel
within the Electric Utility organizations know that
there are two major technical components to interconnected
operation, and they are actively seeking technical
assistance. The two technical areas are: (1) design
and construction of high voltage transmission lines
and substations, and (2) energy management (control)
centers and communications systems.
Design
and construction of transmission lines and substations
is well understood by the utility organizations. However,
the advancing technology of control and communication
systems is an area in which technical assistance may
be needed.
The need
for energy management systems will also force system
operators to come to grips with problems of frequency
regulation, dispatch security and transmission system
contingency planning. Such issues will result in the
development of operating agreements among system operators,
and will include both technical operating issues as
well as compensation schedules. In some cases the
issue of transmission access and loop flows will also
be involved.
8.5 Schedule for System Expansion and Extension
The schedule
for transmission system expansion and extension tends
to be driven by load growth and development of new
generation facilities. However in the case of Central
America, the injection of the concept on an interconnection
between Colombia - Venezuela and Mexico will have
an impact. If plans for such an interconnection become
firm, and the several countries become involved to
the point of becoming committed to the interconnection,
then the schedule for in-country development plans
will be affected.
As dates
for the south - north interconnection firm up, each
country will be forced to adjust its development plans
to accommodate the impending interconnection. Each
country will be required to estimate the timing and
amount of capacity and energy it may receive from
the line. After the quantity and timing are known,
then the focus will shift to how and where. In the
following sections we discuss the possible alignment
of a south - north interconnection.
9. Regional Multi-Terminal HVDC System Interconnections
The desire
for express power transmission between Colombia -
Venezuela and Mexico drives the selection of the type
of transmission line. Given the parameters of magnitude,
distance and specific source and destination, the
selection of a high voltage direct current HVDC line
is indicated. This decision would not be quite so
obvious if there were an existing mature alternating
|