
$7b power grid project on track
Sep 11, 2007 - Issac John - Khaleej Times Online
DUBAI - The first phase of the $7 billion Gulf Cooperation
Council (GCC) power grid will be commissioned by the
first quarter of 2009.
More than 30 per cent of the construction in the
$1.1 billion first phase, which will link Saudi Arabia
to Bahrain, Kuwait and Qatar through 800 kilometres
of transmission lines, was completed at the end of
June. According to the GCC lnterconnection Authority
(GCCIA), given the rapid pace of work on the project,
the first phase would be completed by the end 2008
and it is expected to go into operation in the first
quarter of 2009.
The second phase will link the UAE with Oman. The
resulting two mega grids will be joined in the final
phase. Once the grid is ready, Kuwait and Saudi Arabia
will each receive an extra 1200 MW of power capacity,
the UAE will receive 900 MW, Qatar 750 MW, Bahrain
600 MW and Oman 450 MW.
The GCC power-grid, which will link the six-member
GCC with an integrated electricity network, aims to
reduce the cost of power generation in the six GCC
states.
The Dammam-based GCCIA— which was established in
2001 as a joint stock company with authorised share
capital of $1.1 billion to implement the interconnection
project — said in the first stage of the three-phased
grid, an 800-km 400-kV overhead line will link Kuwait's
Al Zour power station with Doha, and a 400-kV submarine
line will link Saudi Arabia with Bahrain.
A study is currently being conducted with a view
to connecting Saudi Arabia to Egypt, paving the way
for a pan-Arab grid. The main objective of the GCC
power grid is to ensure an emergency power supply
during the shortage of electricity in any of the six
GCC countries.
Work on the project started in September 2005 and
the whole project is expected to be completed by 2010.
"Until recently, it seemed as if the 2010 target was
out of reach because of a lack of progress in several
areas.
Over the last two years a string of new contracts
have been awarded that indicate a new level of determination
to complete the grid," an industry analyst said.
If the entire project is to be completed on schedule
by 2010, it is estimated that total investment cost
would be about $7 billion, although much of this will
be spent on improving internal, domestic power infrastructure.
The GCC countries, riding an economic boom spurred
by record oil revenues and population growth, have
committed to invest $100 billion to generate 100,000
MW of additional power over the next 10 years to meet
demand.
Adnan I. AI Mohaisen, Chief Executive Officer, GCCIA,
in an interview with the Saudi Commerce & Economic
Review, said that the first phase at the project would
be completed by the end 2008 and it is expected to
go into operation by the first quarter at 2009.
The project has been divided into several work packages:
substations, back-to-back HVDC (high voltage direct
current) converter station, submarine cable, overhead
transmission line and the Interconnection Central
Centre. He pointed out that after the completion of
the interconnection project, which potentially can
be linked to other international grids such as EJILST
(Egypt, Jordan, lraq, Lebanon, Syria and Turkey) and
UTCE of Europe for energy interchange, the GCC can
emerge as a major regional power trading market.
According to AI Mohaisen, the most important feature
of the project is the use of a submarine cable, which
will connect Saudi Arabia to Bahrain. Although it
is costlier to install the submerged cable than constructing
a transmission line, it has been found necessary due
to Bahrain being an island and lacking land access
to connect it through overhead lines. He said the
installation of the submarine cable would represent
nearly one-third of the total cost of the interconnection
project. The project will also have the Middle East's
first HVDC station. The 1,800 MW station is necessary
to convert the frequency between Saudi Arabia's transmission
grid and the grids at other GCC countries.
The GCC power grid will be eventually linked to the
Dh2 billion UAE national power grid, the second phase
of which was inaugurated recently. Electricity network
in Sharjah was inter-connected with its peers in Abu
Dhabi and Dubai. The UAE power grid, which will enable
power authorities in each emirate to use or exchange
the reserve power capacity in case of emergency, will
also reduce operations costs and allow easy link of
the UAE to the GCC power grid.
Construction work on the first phase has been progressing
smoothly, although contractors of the projects have
been facing difficulties due to steep rise in aluminium
price. He pointed out that the prices at aluminium
have more than doubled since the contracts were awarded
in 2005.
AI Mohaisen said a major problem facing the project
in the installation of power transmission lines. "We
are encountered with numerous oil and gas pipelines
and pipelines of other utilities in the way of laying
our transmission cables, which have been hampering
our work," he said.
|