een wereldwijd elektriciteitsnet een oplossing voor veel problemen  GENI es una institución de investigación y educación-enfocada en la interconexión de rejillas de electricidad entre naciones.  ??????. ????????????????????????????????????  nous proposons la construction d’un réseau électrique reliant pays et continents basé sur les ressources renouvelables  Unser Planet ist mit einem enormen Potential an erneuerbaren Energiequellen - Da es heutzutage m` glich ist, Strom wirtschaftlich , können diese regenerativen Energiequellen einige der konventionellen betriebenen Kraftwerke ersetzen.  한국어/Korean  utilizando transmissores de alta potência em áreas remotas, e mudar a força via linha de transmissões de alta-voltagem, podemos alcançar 7000 quilómetros, conectando nações e continentes    
What's Geni? Endorsements Global Issues Library Policy Projects Support GENI
Add news to your site >>







About Us

The Transmission Imperative for Renewables

Feb 19, 2011 - Martin Gross - renewableenergyworld.com

It's an interesting time to be involved with electricity. The power industry is on the verge of the biggest changes since the days of Thomas Edison and George Westinghouse. Recent breakthroughs around the world in power transmission systems have made it imperative for the U.S. to develop a more intelligent, flexible, long-haul transmission network that can carry renewable energy from remote locations to major population centers.

RPS Driving Build Out

Today in the U.S., 33 out of 50 states have some kind of renewable standard. These renewable portfolio standards (RPS), and their corresponding deadlines for compliance, have significantly impacted generation spending.

Proposed goals for a national renewable portfolio standard vary from 12 to 25 percent. If the government enacts a national standard, experts estimate that incremental capacity additions of more than 300 GW will be needed. Transmission capacity for this new and mostly remote generation, however, does not exist. With an average construction schedule of 60 months to 72 months for a 500 MW, 345 kV transmission line, it could take well beyond 2025 to build the needed transmission lines.

The North American Electric Reliability Corp.’s (NERC’s) October 2009 publication, “2009 Long Term Reliability Assessment 2009 – 2018,” notes that although existing reserve margins are adequate across the U.S. for the next few years, the first priority must be to expand the grid and increase transmission capacity to handle expected renewable generation growth.

The report concludes by saying: “More than 11,000 miles (or 35 percent) of transmission above 200 kV proposed and projected in this report must be developed on time to ensure reliability over the next five years.” NERC strongly believes that construction siting is the most urgent issue for the electric power industry, now and well into the future.

Bulk Transmission Capacity: A Prerequisite

If utilities are to harvest the vast renewable power potential in remote locations in the U.S., or anywhere in the world, they must be able to move it efficiently from its production point to cities and load centers where people live and work.

Bulk transmission capacity is a prerequisite for large-scale renewable generation. While many renewable power sources’ intermittent nature creates challenges for grid reliability, proven, readily-available and cost-effective transmission technologies exist to mitigate their impact. They are available now and include high voltage direct current (HVDC) and flexible AC transmission systems (FACTS).

Several key transmission projects in the U.S. focus on transmitting renewable generation:

* Southern California Edison continues to add transmission to support wind generation in the Tehachapi region.
* FPL’s NextEra Energy has completed much of its merchant transmission associated with its Horse Hollow Wind Energy Center project in Texas.
* LS Power’s Southwest Intertie will move renewable power from Wyoming and Montana to substations near Las Vegas, using AC and possibly high voltage DC transmission.
* Another LS Power project, Overland Transmission, will apply either high voltage AC or DC circuits across 560 miles to move renewables-fueled generation between eastern Wyoming and southern Idaho.
* San Diego Gas & Electric’s Sunrise PowerLink will play a major role in bringing renewable generation from the Imperial Valley into southern California, even though it was built primarily to ensure system reliability and support load growth. According to the Renewable Energy Transmission Initiative, the Imperial Valley region has potential for 6,870 MW of solar, 3,495 MW of wind and 2,000 MW of geothermal power generation.

Although multiple major transmission projects are underway or nearing construction in the U.S., they are not enough to support RPS requirements. The two key renewable power transmission capacity expansion impediments are:

* The fragmented and time consuming regulatory approval process, and
* The absence of an integrated renewable generation and transmission strategy.

A look at a couple of examples of recent transmission successes in Europe and China provide an idea of what U.S. transmission could look like.

Europe: Visionary Governments Prepare for Offshore Wind

In the North Sea, 81 miles off Germany’s coast, the world’s largest offshore wind farm is connected to the grid using advanced HVDC technology. With HVDC cables lying both underwater and underground, the project’s environmental impact is minimized and the regulatory and siting procedures have been swift. The project connects wind generators and transmits power to a new substation on Germany’s coast. The power is then connected to the existing transmission grid.

The BORWIN 1 offshore wind farm demonstrates how HVDC can effectively accumulate power generated in remote locations and transmit it to load centers. Through the use of HVDC and wind generation, Transpower, the transmission grid operator, expects to avoid 1.5 million tons of CO2 emissions per year by replacing fossil fuel generation.

This summer, an even larger project was launched off Europe’s coast. ABB is working with Transpower to supply an 800 MW power link. This project will use HVDC Light technology to transmit power from the 400 MW Borkum West II wind farm (see Figure 1) and other wind farms to be developed nearby. The wind farms will be connected to an offshore HVDC converter station that will transmit electricity to the onshore HVDC station at Dörpen, on Germany’s northwest coast, via 165 kilometers of underwater and underground DC cables. The Dörpen/West converter station will in turn feed AC power to the mainland grid. At 320 kV, this will be the highest voltage level of extruded cable ever used for HVDC. State-of-the-art transmission technologies like these are integrating renewable energy sources efficiently, ensuring grid reliability and stability and lowering environmental impact.


China continues to set the example and lead the way in developing advanced transmission technologies that tap the power of renewable energies without many of the state or national obstacles faced in the U.S. or Europe. For example, ABB recently worked with the State Grid Corp. of China (SGCC) to create the world’s first ultrahigh-voltage direct current (UHVDC) transmission link for commercial operation. ABB believes this project represents the world’s longest and most powerful transmission link (see Figure 2)

.

The ±800 kV Xiangjiaba to Shanghai UHVDC link can transmit up to 7,200 MW of power from the Xiangjiaba hydropower plant in southwest China to Shanghai, the country’s leading industrial and commercial center, which is about 2,000 kilometers away in eastern China. The new link can meet the electricity needs of about 24 million people and sets a new benchmark in terms of voltage levels and transmission capacity, superseding the 600 kV Itaipu transmission line in Brazil, which was also developed by ABB.

The high-capacity power link comprises a single overhead line and occupies less space than the existing system. Moreover, transmission losses on the new line are less than 7 percent; considerably less than the existing 500 kV system. The electricity saved is equivalent to the power needs of around one million people in China.

UHVDC transmission is a new and expanded development of HVDC. It is particularly suitable for vast countries like China and India, where consumption centers are often located far from power sources, including renewables.

Overcoming U.S. Obstacles

While in other parts of the world, governments, regulators, utilities and industries are working toward common goals, many transmission projects in the U.S. have not yet overcome regulatory hurdles.

The good news is there is proof that things can be done differently. In Texas, utilities, multiple regulatory agencies, generation companies and reliability councils are working together to execute a Public Utility Commission (PUC) order effectively, timely and fairly. Hallmark to this activity is the PUC-driven coordination between transmission and generation stakeholders. When completed by the end of 2013, this Texas CREZ (Competitive Renewable Energy Zones) initiative should result in incremental addition of more than 5,000 miles of high voltage AC transmission, allowing 18 GW of renewable generation to be reliably moved from west Texas into Dallas, San Antonio and Austin.

ERCOT consulted other regional transmission organizations, independent organizations, independent system operators and utilities while studying and developing multiple scenarios. The Texas Department of Wildlife provided impact analysis. Based on ERCOT recommendations, the PUC chose one of four CREZ scenarios and ordered its development.

The PUC provided stakeholders with guidelines and protocols, assuring them that neither generation nor transmission investment will be “stranded.” This was done to provide generation stakeholders the assurance they need before building new wind generation.

To comply, wind generators have been busy. Nearly 11 GW of wind power are installed, 450 MW of new wind power are under construction and nearly 13 GW of wind are in development.

The bottom line in Texas is that these projects got off the ground in a matter of years, not decades.

Swift regulatory and siting procedures, fair cost allocation and political courage to execute are needed to resolve key obstacles delaying renewable energy and related transmission build out across the U.S. and other nations grappling with this issue.

A progressive PUC, like the Texas PUC, and cooperation between the various regulatory agencies that have agreed on common goals and executed the reviews and permits needed to keep schedules on track, can lead to success.

Idaho Gov. C.L. Otter recently said, “The recent economic recession has slowed the growth in demand for electricity, but we cannot squander this opportunity to address future needs. It is clear that coordination among states, the federal government, all segments of the industry and non-governmental organizations is essential for the region to meet its clean energy needs.”

The Texas CREZ is an excellent example of how things can get done in the U.S. A visionary PUC with political support, a coordinated regulatory process, and the courage by everyone involved combines for a favorable environment for sustainable renewable power growth. This model can, and hopefully soon will be, applied across the U.S. as it is elsewhere.

Once a fast track, integrated renewable power and transmission strategy is set in motion, the U.S. will meet its RPS targets and be positioned to take full advantage of these rapidly-growing transmission technologies, systems and capacity already being built and implemented elsewhere throughout the world.





Updated: 2016/06/30

If you speak another language fluently and you liked this page, make a contribution by translating it! For additional translations check out FreeTranslation.com (Voor vertaling van Engels tot Nederlands) (For oversettelse fra Engelsk til Norsk)
(Для дополнительных переводов проверяют FreeTranslation.com )