|  
  Energy Law Alert: Ninth Circuit
                            Decision Further Dismantles an Already Weakened Federal
                            Transmission Siting Authority2011 - Stoel Rives, LLP Congress' experiment with establishing federal siting
                            authority for transmission lines suffered another
                            setback after a Ninth Circuit Court of Appeals decision
                            issued yesterday, February 1, 2011, vacated the Department
                            of Energy's ("DOE") 2007 Transmission Congestion
                            Study (the "Congestion Study") that had
                            designated national interest electric transmission
                            corridors in mid-Atlantic and Southwestern states.
                            This ruling is the latest of three court and agency
                            decisions that have limited or undermined the federal
                            siting authority established at Federal Power Act
                            section 216 by the Energy Policy Act of 2005 ("EPAct
                            2005"). Congress created section 216 to confront concerns
                            that states were acting too slowly in siting new
                            transmission lines needed to address growing reliability
                            and congestion problems. In part, section 216 directs
                            the DOE to study transmission congestion in consultation
                            with the states, and designate certain transmission-constrained
                            areas as national interest electric transmission
                            corridors ("NIETCs"). Section 216 also
                            grants the Federal Energy Regulatory Commission ("FERC")
                            authority to issue permits to construct transmission
                            facilities in these NIETCs under certain circumstances.
                            Congress also provided that an applicant who receives
                            a permit to construct transmission in a NIETC would
                            be granted with the authority to acquire rights-of-way
                            by eminent domain. In sum, section 216 had the potential
                            to uncork the transmission bottleneck, but that potential
                            has not materialized. In yesterday's decision, California Wilderness Coalition
                            v. U.S. Dept. of Energy, No. 08-71074 (9th Cir. Feb.
                            1, 2011), the Ninth Circuit vacated the DOE's Congestion
                            Study as well as the NIETCs designated therein, prompting
                            the DOE to start anew. In vacating the DOE's actions,
                            the Ninth Circuit ruled that the DOE (1) failed to
                            properly consult with affected states in preparing
                            the Congestion Study, as required by section 216,
                            and (2) failed to consider the environmental effects
                            of designating NIETCs under the National Environmental
                            Protection Act ("NEPA"). One judge, Circuit
                            Judge Ikuta, dissented, arguing that although the
                            DOE had failed to properly consult the states, the
                            error did not impact the NIETC designation process.
                            Judge Ikuta further argued that the Congestion Study
                            itself did not constitute a federal plan that precisely
                            established the scope and limits of transmission
                            development, and therefore any attempt to prepare
                            an environmental analysis would have created little
                            more than a speculative study containing estimates
                            of potential development over a vast geographic area.
                            He concluded that the appropriate time for NEPA determination
                            was when specific transmission projects were proposed.
                            In that regard, Judge Ikuta argued that the majority
                            decision defied common sense. Yesterday's Ninth Circuit ruling added to the effective
                            dismantling of section 216 by the Fourth Circuit
                            Court of Appeals and by FERC itself. In 2006, shortly
                            after the enactment of EPAct 2005, FERC issued a
                            rulemaking order (Order No. 689) that detailed the
                            various requirements and procedures for applications
                            submitted under section 216. FERC's rules created
                            a cumbersome, multi-year process for obtaining a
                            federal permit to construct transmission within a
                            NIETC, and in doing so FERC effectively discouraged
                            participation in the program altogether. Then, in 2009, the Fourth Circuit ruled in Piedmont
                            Environmental Council v. FERC, No. 07-1651 (4th Cir.
                            Feb. 18, 2009), that FERC has no authority to issue
                            permits under section 216 when a state denies an
                            application for siting transmission facilities. Rather,
                            the Fourth Circuit found that FERC's backstop authority
                            is limited to instances where a state withholds approval
                            for more than a year. Together with these earlier decisions, yesterday's
                            ruling in California Wilderness Coalition leaves
                            the question—what remains of section 216? For more information about yesterday's decision
                            or other transmission issues, please contact: Marcus Wood at (503) 294-9434 or mwood@stoel.comJason Johns at (503) 294-9618 or jajohns@stoel.com
 Sarah Johnson Phillips at (612) 373-8843 or sjphillips@stoel.com
 
   |