   
Exploration of Resource and 
  Transmission Expansion Decisions in 
  the Western Renewable Energy Zone 
  Initiative
Feb 24, 2010 - eetd.lbl.gov 
Abstract 
  Building transmission to reach renewable energy (RE) goals requires coordination among
  renewable developers, utilities and transmission owners, resource and transmission planners,
  state and federal regulators, and environmental organizations. The Western Renewable Energy
  Zone (WREZ) initiative brings together a diverse set of voices to develop data, tools, and a
  unique forum for coordinating transmission expansion in the Western Interconnection. In this
  report we use a new tool developed in the WREZ initiative to evaluate possible renewable
  resource selection and transmission expansion decisions. We evaluate these ecisions under a
  number of alternative future scenarios centered on meeting 33% of the annual load in the
  Western Interconnection with new renewable resources located within WREZ-identified
  resource hubs.
  Of the renewable resources in WREZ resource hubs, and under the assumptions described in this
  report, our analysis finds that wind energy is the largest source of renewable energy procured to
  meet the 33% RE target across nearly all scenarios analyzed (38-65%). Solar energy is almost
  always the second largest source (14-41%). Solar exceeds wind by a small margin only when solar
  thermal energy is assumed to experience cost reductions relative to all other technologies. 
  Biomass, geothermal, and hydropower are found to represent a smaller portion of the selected
  resources, largely due to the limited resource quantity of these resources identified within the
  WREZ-identified hubs (16-23% combined). We find several load zones where wind energy is the
  least cost resource under a wide range of sensitivity scenarios. Load zones in the Southwest, on
  the other hand, are found to switch between wind and solar, and therefore to vary transmission
  expansion decisions, depending on uncertainties and policies that affect the relative economics of
  each renewable option. Uncertainties and policies that impact bus-bar costs are the most important
  to evaluate carefully, but factors that impact transmission costs and the relative market value of
  each renewable option can also be important. Under scenarios in which each load zone must meet
  33% of its load with delivered renewable energy from the WREZ-identified resource hubs, the
  total transmission investment required to meet the 33% west-wide RE target is estimated at
  between $22 billion and $34 billion. Although a few of the new transmission lines are very long—
  over 800 miles—most are relatively short, with average transmission distances ranging from 230-315 miles, depending on the scenario. Needed transmission expenditure are found to decline to
  $17 billion if wide use of renewable energy credits is allowed; consideration of renewable
  resources outside of WREZ-identified hubs would further reduce this transmission cost estimate. 
  Even with total transmission expenditures of $17-34 billion, however, these costs still represent
  just 10-19% of the total delivered cost of renewable energy. 
Full Article  
   
  
  |