  
                            Kenya joins regional power supply plan
                          May 18, 2006 
                            - The Nation  
                          Kenya is among three countries set to 
                            benefit from a Sh 47.5 bn ($ 660 mm) electricity generation 
                            project. Kenya was working alongside Tanzania and 
                            Zambia on a joint interconnection project expected 
                            to help the countries access electricity from southern 
                            Africa, Energy assistant minister Mwangi Kiunjuri 
                            said. This is also expected to reduce electricity 
                            costs and eradicate shortages.  Mr Kiunjuri made the 
                            announcement while reading a joint communique after 
                            a meeting between ministers from the three countries 
                            in Mombassa. "The project will also increase opportunities 
                            for regional electricity trade within the framework 
                            of the New Partnership for Africa's Development (NEPAD)," 
                            he said. Present were Zambia's minister for Energy 
                            and Water Development, Mr Felix Mutati, and Tanzania's 
                            minister for Energy and Minerals, Dr Ibrahim Msabaha. 
                             The project is to be developed in two stages. Phase 
                            One will transfer more than 200 MW from the Southern 
                            African Power Pool at a cost of Sh 25 bn ($ 358 mm). 
                            "Phase Two, which is estimated to cost Sh 21 bn ($ 
                            302 mm), will have a transfer capacity of 400 MW," 
                            Mr Kiunjuri said. The first phase is scheduled to 
                            be completed by 2009 and the second in 2014. In Phase 
                            Two, a second circuit is to be added onto the Zambia-Tanzania 
                            inter-connector and the section between Singida and 
                            Arusha in Tanzania would be reinforced. "Apart from 
                            transmission of power, the towers carrying the high 
                            voltage transmission conductors will also carry low 
                            voltage conductors for rural electrification along 
                            the transmission corridor," the assistant minister 
                            said.  The innovative design would enable communities 
                            living close to the line to be supplied with electricity, 
                            which Mr Kiunjuri said would enhance the social and 
                            economic development of Kenya, Tanzania and Zambia. 
                            "A telecommunications fibre optic cable will be installed 
                            on the transmission line, to enhance communication 
                            links between the East African Community and SADC 
                            member States," he said.  Negotiations for funding 
                            and implementing the Tanzania-Kenya inter-connector 
                            components with a Dutch firm, Vatech Elin Holec High 
                            Voltage, are at an advanced stage. Financing under 
                            the concessionary Dutch programme is expected to be 
                            in place by early 2007. Construction should start 
                            soon thereafter and is projected to be completed in 
                            24 months, Mr Kiunjuri said.  The technical, economic, 
                            financial and environmental studies on the Zambia-Tanzania 
                            inter-connector, which will be the second phase, have 
                            been completed. With regard to the reinforcement of 
                            the transmission system within Tanzania to facilitate 
                            transfer of power to Kenya, the environmental studies 
                            are in progress and will be completed in May, he said. 
                             The three governments had secured grants worth Sh 
                            57 mm or ($ 800,000) for preparatory activities on 
                            the project from the NEPAD Infrastructure Project 
                            Preparatory Fund. A consortium of consultants had 
                            been hired as transaction advisers to provide financial, 
                            technical and legal advisory services for the initial 
                            stage of the project. Source: The Nation 
                          |